A project requires the completion of 9 activities, \(A\) to \(I\). The project is due to be completed in 13 days.
The directed network diagram shows these activities with their completion times in days.
- Use the information from the network diagram to complete the Gantt chart, including the critical path and all other activities required for the project. (3 marks)
--- 0 WORK AREA LINES (style=lined) ---
- List all activities, not on the critical path, which could be occurring at midday on day 8. (1 mark)
--- 3 WORK AREA LINES (style=lined) ---