Concrete is poured to make a pathway.

The dimensions of the slab are shown in the diagram below.
 

If the concrete costs $180 per cubic metre to pour, what is the cost of pouring the slab?

  1. \($864\)
  2. \($2880\)
  3. \($22\ 600\)
  4. \($86\ 400\)
Show Answers Only

\(A\)

Show Worked Solution

\(30\ \text{cm}=0.3\ \text{m}\)

\(\text{Volume of slab}\) \(=8\times 0.3\times 2\)
  \(=4.8\ \text{m}^3\)

 

\(\text{Cost of pouring slab}\) \(=4.8\times $180\)
  \(=$864\)

\(\Rightarrow\ A\)