The directed network shows the sequence of activities required to complete a project.

The time to complete each activity, in hours, is also shown.

What is the earliest starting time (EST) in hours for activity \(K\)?

  1. 10
  2. 11
  3. 12
  4. 13
Show Answers Only

\(C\)

Show Worked Solution

\(\text{EST}(K)\ \text{occurs when all possible activities before it are complete.}\)

\(\text{There are three possible routes to get to}\ K.\)

\(\text{EST}(K)\) \(=\max(4+3+5,\ \ 4+6+1,\ \ 4+3+2+1)\)
  \(=\max(12,11,10)\)
  \(=12\ \text{hours}\)

 

\(\Rightarrow C\)