Networks, STD2 2026 HSC 7 MC

The directed network shows the sequence of activities required to complete a project.

The time to complete each activity, in hours, is also shown.

What is the earliest starting time (EST) in hours for activity \(K\)?

  1. 10
  2. 11
  3. 12
  4. 13
Show Answers Only

\(C\)

Show Worked Solution

\(\text{EST}(K)\ \text{occurs when all possible activities before it are complete.}\)

\(\text{There are three possible routes to get to}\ K.\)

\(\text{EST}(K)\) \(=\max(4+3+5,\ \ 4+6+1,\ \ 4+3+2+1)\)
  \(=\max(12,11,10)\)
  \(=12\ \text{hours}\)

 

\(\Rightarrow C\)

Filed Under: Critical Path Analysis (Y12) Tagged With: Band 4, smc-6916-55-EST/LST/Float Times

Networks, STD2 EQ-Bank 28

Lena is opening a new café. The project requires the completion of 7 activities, \(A\) to \(G\). The project is due to be completed in 15 days.

The directed network diagram shows these activities with their completion times in days.
  

   
  
  1. Use the information from the network diagram to complete the Gantt chart, including the critical path and all other activities required for the project.   (3 marks)

    --- 0 WORK AREA LINES (style=lined) ---

      

      
  2. List all activities, not on the critical path, which could be occurring at midday on day 7.   (1 mark)

    --- 3 WORK AREA LINES (style=lined) ---

Show Answers Only

a.

b.    \(B\text{, }D\text{ and }E\)

Show Worked Solution

a.

 
b.
    \(\text{By inspection of the Gantt chart.}\)

\(\text{Activities which could be occurring at }\approx 6.5\ \text{on chart (midday day 7):}\)

\(B\text{, }D\text{ and }E\)

Filed Under: Critical Path Analysis (Y12) Tagged With: Band 4, Band 5, smc-6916-35-Gantt Charts, syllabus-2027

Networks, STD2 EQ-Bank 27

A project requires the completion of 8 activities, \(A\) to \(H\). The project is due to be completed in 16 days.

The directed network diagram shows these activities with their completion times in days.
  

   
  
  1. Use the information from the network diagram to complete the Gantt chart, including the critical path and all other activities required for the project.   (3 marks)

    --- 0 WORK AREA LINES (style=lined) ---

      


      

  2. List all activities, not on the critical path, which could be occurring at midday on day 9.   (1 mark)

    --- 3 WORK AREA LINES (style=lined) ---

Show Answers Only

a.

b.    \(C,  D\ \text{and}\ F\)

Show Worked Solution

a.

 
b.   
\(\text{By inspection of the Gantt chart.}\)

\(\text{Activities which could be occurring at}\ \approx 8.5\ \text{on chart (midday day 9):}\)

\(C, D\ \text{and}\ F\)

Filed Under: Critical Path Analysis (Y12) Tagged With: Band 4, Band 5, smc-6916-35-Gantt Charts, syllabus-2027

Networks, STD2 EQ-Bank 2 MC

The Gantt chart below shows the activities involved in organising a school sports carnival. 
  

   
Which activity has the greatest float time?

  1. \(\text{B}\)
  2. \(\text{D}\)
  3. \(\text{E}\)
  4. \(\text{G}\)
Show Answers Only

\(B\)

Show Worked Solution

\(\text{From the Gantt chart, the dashed extensions show:}\)

\(\text{B: float = 3 hours}\)

\(\text{D: float = 5 hours}\)

\(\text{E: float = 3 hours}\)

\(\text{G: float = 0 (critical path, no dashed extension)}\)

\(\text{Activity D has the greatest float time (5 hours).}\)

\(\Rightarrow B\)

Filed Under: Critical Path Analysis (Y12) Tagged With: Band 3, smc-6916-35-Gantt Charts, smc-6916-55-EST/LST/Float Times, syllabus-2027

Networks, STD2 EQ-Bank 6 MC

The Gantt chart below shows the activities involved in organising a community market day. Critical path activities are shown as solid bars and non-critical activities show available float as dashed extensions.
  


  

Activity \(D\) is delayed by 7 hours and activity \(B\) is delayed by 1 hour. What is the new minimum completion time for the project?

  1. 14 hours
  2. 15 hours
  3. 16 hours
  4. 22 hours
Show Answers Only

\(C\)

Show Worked Solution

\(\text{From the Gantt chart:}\)

\(\text{D has float of 5 hours. Delay of 7 exceeds float by 2.}\)

\(\text{B has float of 3 hours. Delay of 1 is within float.}\)

\(\text{Only the delay to D affects completion time.}\)

\(\text{New minimum} = 14+2 = 16 \text{ hours}\)

\(\Rightarrow C\)

Filed Under: Critical Path Analysis (Y12) Tagged With: Band 4, smc-6916-35-Gantt Charts, smc-6916-55-EST/LST/Float Times, syllabus-2027

Networks, STD2 EQ-Bank 25

The construction of a new reptile exhibit is a project involving nine activities, \(A\) to \(I\). The network diagram below shows the activities and their completion times in weeks. Some values are missing.

The Gantt chart below has been created for this project.

  1. Using the Gantt chart, identify the critical path.   (1 mark)

    --- 2 WORK AREA LINES (style=lined) ---

  2. Use the Gantt chart to determine the missing values in the network diagram.   (2 marks)

    --- 4 WORK AREA LINES (style=lined) ---

  3. Activity \(E\) is delayed by 8 weeks. Using the Gantt chart, explain whether this will affect the minimum completion time of the project.   (2 marks)

    --- 5 WORK AREA LINES (style=lined) ---

Show Answers Only

a.    \(ACDFGI\)

b.    \(\text{B} = 5 \text{ weeks, H} = 7 \text{ weeks}\)

c.    \(\text{From the Gantt chart, activity E has a float of 6 weeks (see the dashed}\)

\(\text{extension from week 10 to 16).}\)

\(\text{The delay of 8 weeks exceeds the float of 6 weeks.}\)

\(\text{The project will be delayed by } 8-6 = 2 \text{ weeks.}\)

\(\text{New minimum completion time} = 25+2 = 27 \text{ weeks.}\)

Show Worked Solution

a.    \(\text{The critical path is the continuous solid bar on row 1 of the Gantt chart.}\)

\(\text{Critical path:}\ ACDFGI\)
 

b.    \(\text{Activities B and H are not labelled in the network diagram.}\)

\(\text{From the Gantt chart:}\)

\(\text{B starts at week 0, ends at week 5} \to \text{duration} = 5 \text{ weeks}\)

\(\text{H starts at week 13, ends at week 20} \to \text{duration} = 7 \text{ weeks}\)
 

c.    \(\text{From the Gantt chart, activity E has a float of 6 weeks (see the dashed}\)

\(\text{extension from week 10 to 16).}\)

\(\text{The delay of 8 weeks exceeds the float of 6 weeks.}\)

\(\text{The project will be delayed by } 8-6 = 2 \text{ weeks.}\)

\(\text{New minimum completion time} = 25+2 = 27 \text{ weeks.}\)

Filed Under: Critical Path Analysis (Y12) Tagged With: Band 3, Band 4, Band 5, smc-6916-35-Gantt Charts, smc-6916-40-Critical Path Adjustments, smc-6916-55-EST/LST/Float Times, syllabus-2027

Networks, STD2 EQ-Bank 18

A Gantt chart for a project with activities \(A, B, C, D, E, F, G\) and \(H\) has been created where all times are in hours. The Gantt chart can be used to complete the missing information on the edges in the network diagram.
  

  
  1. Use the Gantt chart to determine the three missing values in the network diagram.   (3 marks)

    --- 3 WORK AREA LINES (style=lined) ---

  2. State the minimum completion time for the project.   (1 mark)

    --- 2 WORK AREA LINES (style=lined) ---

Show Answers Only

a.    \(\text{C} = 4 \text{ hours, D} = 5 \text{ hours, E} = 7 \text{ hours}\)

b.    \(26 \text{ hours}\)

Show Worked Solution

a.    \(\text{Using the Gantt chart}\)

\(\text{C (between A and F):} \)

\(\Rightarrow\ \text{Starts hour 7, ends hour 11 = 4 hours duration}\)

\(\text{D (between B and G):}\)

\(\Rightarrow\ \text{Starts hour 3, ends hour 9 = 6 hours duration}\)

\(\text{E (between B and H):}\)

\(\Rightarrow\ \text{Starts hour 3, ends hour 13 = 10 hours duration}\)
 

b.    \(\text{From the Gantt chart, the project ends at hour 26.}\)

\(\text{Minimum completion time} = 26 \text{ hours}\)

Filed Under: Critical Path Analysis (Y12) Tagged With: Band 3, Band 4, smc-6916-35-Gantt Charts, syllabus-2027

Networks, STD2 EQ-Bank 26

A project requires the completion of 9 activities, \(A\) to \(I\). The project is due to be completed in 13 days.

The directed network diagram shows these activities with their completion times in days.
 

   

  1. Use the information from the network diagram to complete the Gantt chart, including the critical path and all other activities required for the project.   (3 marks)

    --- 0 WORK AREA LINES (style=lined) ---

       

  2. List all activities, not on the critical path, which could be occurring at midday on day 8.   (1  mark)

    --- 3 WORK AREA LINES (style=lined) ---

Show Answers Only

a.    
     

b.    \(C\ \text{and}\ E\)

Show Worked Solution

a.    
         

 
b.
    \(\text{By inspection of the Gantt chart}\)

\(\text{Activities which could be occurring $\approx$ 7.5 on chart (midday day 8):}\)

\(C\ \text{and}\ E\)

Filed Under: Critical Path Analysis (Y12) Tagged With: Band 4, Band 5, smc-6916-35-Gantt Charts, syllabus-2027

Networks, STD2 EQ-Bank 5 MC

The network diagram shows the time needed for each step in order to complete a project.
 

   

What is the float time of activity \(E\)?

  1. 2
  2. 5
  3. 7
  4. 9
Show Answers Only

\(B\)

Show Worked Solution

\(\text{Float time} = LST\ (\text{activity}\ E)-EST\ (\text{activity}\ E)=7-2=5\)

\(\Rightarrow B\)

Filed Under: Critical Path Analysis (Y12) Tagged With: Band 4, smc-6916-55-EST/LST/Float Times

Networks, STD2 N3 2025 HSC 19

The activities and corresponding durations in days for a project are shown in the network diagram.
 

 

  1. Complete the table showing the immediate prerequisites for each activity. Indicate with an \(\text{X}\) any activities without any immediate prerequisites.   (2 marks)

\begin{array} {|c|c|}
\hline
\rule{0pt}{2.5ex} \text{Activity} \rule[-1ex]{0pt}{0pt} & \text{Immediate prerequisite(s)} \\
\hline
\rule{0pt}{2.5ex} B \rule[-1ex]{0pt}{0pt} &  \\
\hline
\rule{0pt}{2.5ex} E \rule[-1ex]{0pt}{0pt} &  \\
\hline
\rule{0pt}{2.5ex} F \rule[-1ex]{0pt}{0pt} &  \\
\hline
\end{array}

  1. Find the critical path for this project AND state the minimum duration for the project.   (2 marks)

--- 4 WORK AREA LINES (style=lined) ---

  1. The duration of activity \( A \) is increased by 2. Does this affect the critical path for the project? Give a reason for your answer.   (1 mark)

--- 4 WORK AREA LINES (style=lined) ---

Show Answers Only

a.           

\begin{array} {|c|c|}
\hline
\rule{0pt}{2.5ex} \text{Activity} \rule[-1ex]{0pt}{0pt} & \text{Immediate prerequisite(s)} \\
\hline
\rule{0pt}{2.5ex} B \rule[-1ex]{0pt}{0pt} & \text{X} \\
\hline
\rule{0pt}{2.5ex} E \rule[-1ex]{0pt}{0pt} & C,D \\
\hline
\rule{0pt}{2.5ex} F \rule[-1ex]{0pt}{0pt} & E \\
\hline
\end{array}

  
b.   \(\text{Critical Path:}\ BDEFH\)

\(\text{Minimum Duration}\ =4+5+5+7+5=26\ \text{days}\)
 

c.   \(\text{If duration of activity \(A\) is increased by 2:}\)

\(\text{The critical path remains unchanged (EST of activity \(E\) remains = 9)}\)

Show Worked Solution

a.   

\begin{array} {|c|c|}
\hline
\rule{0pt}{2.5ex} \text{Activity} \rule[-1ex]{0pt}{0pt} & \text{Immediate prerequisite(s)} \\
\hline
\rule{0pt}{2.5ex} B \rule[-1ex]{0pt}{0pt} & \text{X} \\
\hline
\rule{0pt}{2.5ex} E \rule[-1ex]{0pt}{0pt} & C,D \\
\hline
\rule{0pt}{2.5ex} F \rule[-1ex]{0pt}{0pt} & E \\
\hline
\end{array}

  
b.   

\(\text{Critical Path:}\ BDEFH\)

\(\text{Minimum Duration}\ =4+5+5+7+5=26\ \text{days}\)
 

c.   \(\text{If duration of activity \(A\) is increased by 2:}\)

\(\text{The critical path remains unchanged (EST of activity \(E\) remains = 9)}\)

♦ Mean mark (c) 46%.

Filed Under: Critical Path Analysis (Y12), Critical Paths Tagged With: Band 3, Band 4, Band 5, smc-6916-30-Scanning Both Ways, smc-916-30-Scanning Both Ways

Networks, STD2 N3 2024 HSC 39

A project involving nine activities is shown in the network diagram.

The duration of each activity is not yet known.
 

The following table gives the earliest start time (EST) and latest start time (LST) for three of the activities. All times are in hours.

\begin{array} {|c|c|c|}
\hline
\rule{0pt}{2.5ex} \textit{Activity} \rule[-1ex]{0pt}{0pt} & EST & LST \\
\hline
\rule{0pt}{2.5ex} A \rule[-1ex]{0pt}{0pt} & \ \ \ \ \ \ 0\ \ \ \ \ \  & \ \ \ \ \ \ 2\ \ \ \ \ \  \\
\hline
\rule{0pt}{2.5ex} C \rule[-1ex]{0pt}{0pt} & 0 & 1 \\
\hline
\rule{0pt}{2.5ex} I \rule[-1ex]{0pt}{0pt} & 12 & 12 \\
\hline
\end{array}

  1. What is the critical path?   (1 mark)

    --- 2 WORK AREA LINES (style=lined) ---

  2. The minimum time required for this project to be completed is 19 hours.
  3. What is the duration of activity \(I\)?   (1 mark)

    --- 2 WORK AREA LINES (style=lined) ---

  4. The duration of activity \(C\) is 3 hours.
  5. What is the maximum amount of time that could occur between the start of activity \(F\) and the end of activity \(H\)?   (1 mark)

    --- 2 WORK AREA LINES (style=lined) ---

Show Answers Only

a.   \(\text{Critical Path:}\ BEGI\)

b.   \(\text{Duration of}\ I =7\ \text{hours}\)

c.  \(\text{Max time}\ =8\ \text{hours}\)

Show Worked Solution

a.   \(\text{Activity}\ A\ \text{and}\ C: \ LST \gt EST\)

\(\Rightarrow\ \text{Activity}\ A\ \text{and}\ C\ \text{not on critical path.}\)

\(\text{Critical Path:}\ BEGI\)
 

♦ Mean mark (a) 43%.

b.   \(\text{Duration of}\ I = 19-12=7\ \text{hours}\)
 

c.   \(\text{Since}\ C + F + H + I\ \text{is not a critical path:}\)

\(C + F + H + I = 18\ \text{or less (C.P. = 19 hours)}\)

\(3+F+H+7 = 18\ \text{or less}\)

\(\Rightarrow\ F+H = 8\ \text{or less}\)

\(\therefore\ \text{Max time from start of}\ F\ \text{to end of}\ H = 8\ \text{hours}\)

♦♦♦ Mean mark (c) 10%.

Filed Under: Critical Path Analysis (Y12), Critical Paths Tagged With: Band 4, Band 5, Band 6, smc-6916-20-Forward Scanning, smc-6916-30-Scanning Both Ways, smc-916-20-Forward Scanning, smc-916-30-Scanning Both Ways

Networks, STD2 N3 2023 HSC 31

A function centre employs staff so that all necessary tasks can be completed between the end of one function and the beginning of the next function.

The network diagram shows the time taken in hours for the tasks that need to be completed.
 


 

  1. Find the TWO critical paths.   (2 marks)

    --- 4 WORK AREA LINES (style=lined) ---

  2. The function centre wants to decrease the length of each critical path by 3 hours. They can do this by hiring more staff to do ONE of the tasks so it takes less time to complete.
  3. For which task should the centre hire more staff, and how long should that task take to ensure all tasks can be completed in 14 hours?   (2 marks) 

    --- 4 WORK AREA LINES (style=lined) ---

Show Answers Only

a.    `HIGC and HIK`

b.    `text{More staff should be hired for task}\ I.`

`text{By decreasing task}\ I\ text{by 3 hours (so it takes 4 hours), the}`

`text{critical path of the network reduces to 14 hours.}`

Show Worked Solution

a.    `text{Scanning both ways:}`
 

`text{Critical paths:}\ HIGC and HIK`

♦ Mean mark (a) 46%.

 
b. 
   `text{More staff should be hired for task}\ I.`

`text{By decreasing task}\ I\ text{by 3 hours (so it takes 4 hours), the}`

`text{critical path of the network reduces to 14 hours.}`

Mean mark (b) 52%.

Filed Under: Critical Path Analysis (Y12), Critical Paths Tagged With: Band 4, Band 5, smc-6916-30-Scanning Both Ways, smc-6916-40-Critical Path Adjustments, smc-916-30-Scanning Both Ways, smc-916-40-Critical Path Adjustments

Networks, STD2 N3 2022 HSC 3 MC

The network diagram shows the time needed for each step in order to complete a project.
 


 

What is the critical path to complete the project?

  1. `ACI`
  2. `ADG`
  3. `BEH`
  4. `BEFG`
Show Answers Only

`B`

Show Worked Solution

`text{Critical Path:}\ ADG`

`=>B`

Filed Under: Critical Path Analysis (Y12), Critical Paths Tagged With: Band 4, smc-6916-20-Forward Scanning, smc-916-20-Forward Scanning

Networks, STD2 N3 2021 FUR1 6

The directed graph below shows the sequence of activities required to complete a project.

The time taken to complete each activity, in hours, is also shown.
 

The minimum completion time for this project is 18 hours.

The time taken to complete activity `E` is labelled  `x`.

What is the maximum value of  `x`?   (2 marks)

--- 4 WORK AREA LINES (style=lined) ---

Show Answers Only

`text(3 hours)`

Show Worked Solution

`text{Consider all possible network paths:}`

`ADHJ \ -> \ text{18 hours}`

`BEJ \ -> \ (12 + x) \ text{hours}`

`CGFEJ \ -> \  (15 + x) \ text{hours}`

`CGIJ \ -> \ text{18 hours}`
 

`text{Minimum completion time = 18 hours}`

`=>\ text{No path can be longer than 18 hours}`

`:. \ x_text{max} = 3 \ text{hours}`

Filed Under: Critical Path Analysis (Y12), Critical Paths Tagged With: Band 5, smc-6916-20-Forward Scanning, smc-6916-40-Critical Path Adjustments, smc-916-20-Forward Scanning, smc-916-40-Critical Path Adjustments

Networks, STD2 N3 2021 HSC 36

A project requires completion of 11 tasks  `A, B, C, . . . , K.`

A network diagram for the project giving the completion time for each task, in minutes, is shown.
 

  1. Find the minimum time to complete the project.   (1 mark)

    --- 1 WORK AREA LINES (style=lined) ---

  2. State the critical path for this project.   (1 mark)

    --- 2 WORK AREA LINES (style=lined) ---

  3. A new task, `X`, is to be added to the project. The earliest starting time for `X` is 17 minutes, the latest starting time for `X` is 18 minutes and `X` has a completion time of 12 minutes.
  4. Add task `X` to the given network diagram above AND state the float time for this task.   (3 marks)

    --- 4 WORK AREA LINES (style=lined) ---

Show Answers Only

a.    `40 \ text{minutes}`

b.    `A – C – D – E – G – J – K`

c.    `text{Float time = 1minute}`

Show Worked Solution
a.    `text{Scanning forwards:}`

♦ Mean mark part (a) 37%.

 


 
`text{Minimum completion time} = 40 \ text{minutes}`
♦ Mean mark part (b) 44%.
 
 
b.   `text{Critical Path:} \ A C D E G J K`
 
 
♦♦ Mean mark part (c) 32%.
c.   
`text{Float time}\ (X)=18-17= 1 \ text{minute}`

Filed Under: Critical Path Analysis (Y12), Critical Paths Tagged With: Band 5, smc-6916-20-Forward Scanning, smc-916-20-Forward Scanning

Networks, STD2 N3 2020 HSC 26

The preparation of a meal requires the completion of all activities `A` to `J`. The network diagram shows the activities and their completion times in minutes.
 


 

  1. What is the minimum time needed to prepare the meal?   (1 mark)

    --- 1 WORK AREA LINES (style=lined) ---

  2. List the activities which make up the critical path for this network.   (2 marks)

    --- 5 WORK AREA LINES (style=lined) ---

  3. Complete the table below, showing the earliest start time and float time for activities `A` and `G`   (2 marks)
     

    --- 0 WORK AREA LINES (style=lined) ---

Show Answers Only

a.    `46 \ text{minutes}`

b.    `C – D – E – F – H – I`

c.   

Show Worked Solution

a.     `text{Scan forwards and backwards (to answer all parts):}`

♦♦ Mean mark part (a) 31%.
 


 

`text{Minimum time} = 46 \ text{minutes}`
 

b.     `C – D – E – F – H – I`

Mean mark part (b) 51%.

 

c.  `text{Scan backwards (see above):}`

♦♦ Mean mark part (c) 22%.
  

Filed Under: Critical Path Analysis (Y12), Critical Paths Tagged With: Band 5, smc-6916-30-Scanning Both Ways, smc-916-30-Scanning Both Ways

Networks, STD2 N3 2019 FUR2-N 2

The construction of the new reptile exhibit is a project involving nine activities, `A` to `I`.

The directed network below shows these activities and their completion times in weeks.
 


 

  1. Which activities have more than one immediate predecessor?   (1 mark)

    --- 1 WORK AREA LINES (style=lined) ---

  2. Write down the critical path for this project.   (1 mark)

    --- 1 WORK AREA LINES (style=lined) ---

  3. What is the latest start time, in weeks, for activity `B`?   (1 mark)

    --- 2 WORK AREA LINES (style=lined) ---

Show Answers Only

a.    `D, G and I`

b.    `text(See Worked Solutions)`

c.    `2\ text(weeks)`

Show Worked Solution

a.   `D, G and I`
  

b.   `text(Scanning forwards and backwards:)`
 

​
 

`text(Critical Path:)\ ACDFGI`
  

c.    `text{LST (activity}\ B text{)}=7-5=2\ text(weeks)`

Filed Under: Critical Path Analysis (Y12), Critical Paths Tagged With: Band 3, Band 4, smc-6916-30-Scanning Both Ways, smc-916-30-Scanning Both Ways

Networks, STD2 N3 EQ-Bank 30

A project involves nine activities, `A` to `I`.

The immediate predecessor(s) of each activity is shown in the table below.

\begin{array} {|c|c|}
\hline \ \ \textbf{Activity}\ \  &  \textbf{Immediate} \\  & \textbf{predecessor(s)}  \\
\hline \rule{0pt}{2.5ex} A \rule[-1ex]{0pt}{0pt} & - \\
\hline \rule{0pt}{2.5ex} B \rule[-1ex]{0pt}{0pt} & A \\
\hline \rule{0pt}{2.5ex} C \rule[-1ex]{0pt}{0pt} & A \\
\hline \rule{0pt}{2.5ex} D \rule[-1ex]{0pt}{0pt} & B \\
\hline \rule{0pt}{2.5ex} E \rule[-1ex]{0pt}{0pt} & B, C \\
\hline \rule{0pt}{2.5ex} F \rule[-1ex]{0pt}{0pt} & D  \\
\hline \rule{0pt}{2.5ex} G \rule[-1ex]{0pt}{0pt} & D  \\
\hline \rule{0pt}{2.5ex} H \rule[-1ex]{0pt}{0pt} & E, F  \\
\hline \rule{0pt}{2.5ex} I \rule[-1ex]{0pt}{0pt} & G, H  \\
\hline \end{array}

A directed network for this project will require a dummy activity.

Sketch the network diagram, clearly identifying the dummy activity.   (3 marks)

Show Answers Only

Show Worked Solution

`text(Sketch network diagram:)`
 

`text(The dummy activity needs to be drawn)`

`text(from the end of activity)\ B\ text(to the start)`

`text(of activity)\ E.`

Filed Under: Critical Path Analysis (Y12), Critical Paths Tagged With: Band 5, smc-6916-10-Precedence Tables, smc-6916-50-Dummy Activity, smc-916-10-Table to Network, smc-916-50-Dummy Activity

Networks, STD2 N3 2019 HSC 26

A project requires activities `A` to `F` to be completed. The activity chart shows the immediate prerequisite(s) and duration for each activity.

  1. By drawing a network diagram, determine the minimum time for the project to be completed.   (3 marks)

    --- 8 WORK AREA LINES (style=lined) ---

  2. Determine the float time of the non-critical activity.   (1 mark)

    --- 2 WORK AREA LINES (style=lined) ---

Show Answers Only

a.    `text(15 hours)`

b.    `text(3 hours)`

Show Worked Solution
a.    

 

`text(Scanning forwards:)`

`text(Minimum time = 2 + 6 + 2 + 4 + 1 = 15 hours)`

`text{(Scanning forwards and backwards is highly recommended but not}`

 `text{required in the network diagram.)}`

 

b.    `text(Critical Path is)\ ABDEF.`

♦♦ Mean mark 30%.

`text(Non-critical activity is)\ C.`

`text(Float time)=5-2=3\ text(hours)`

Filed Under: Critical Path Analysis (Y12), Critical Paths Tagged With: Band 4, Band 5, smc-6916-10-Precedence Tables, smc-6916-30-Scanning Both Ways, smc-916-10-Table to Network, smc-916-30-Scanning Both Ways

Networks, STD2 N3 EQ-Bank 3 MC

Identify the critical path through this network.
 


 

  1. `DEGJ`
  2. `DFHK`
  3. `DFGIK`
  4. `DEGIK`
Show Answers Only

`=> D`

Show Worked Solution

`text(Critical Path is the longest)`

`:. DEGIK`

`=> D`

Filed Under: Critical Path Analysis (Y12), Critical Paths Tagged With: Band 3, smc-6916-20-Forward Scanning, smc-916-20-Forward Scanning

Networks, STD2 N3 EQ-Bank 20

A project requires nine activities (A–I) to be completed. The duration, in hours, and the immediate predecessor(s) of each activity are shown in the table below.
 


 

  1. Sketch the network, identifying each activity and its duration.   (2 marks)

    --- 7 WORK AREA LINES (style=lined) ---

  2. Identify the critical path and the minimum completion time of the project.   (2 marks)

    --- 4 WORK AREA LINES (style=lined) ---

Show Answers Only

a. 

 

b.    `text(Critical path is)\ ACFGI.`

`text(20 hours)`

Show Worked Solution

a.    `text(Sketch the network:)`

 

 
b.    `text(Completion time of possible paths:)`

`ABEGI = 4 + 3 + 5 + 4 + 3 = 19\ text(hours)`

`ACFGI = 4 + 7 + 2 + 4 + 3 = 20\ text(hours)`

`ADHI = 4 + 2 + 5 + 3 = 14\ text(hours)`
 

`:.\ text(Critical path is)\ ACFGI.`

`:.\ text{Minimum completion time  = 20 hours}`

Filed Under: Critical Path Analysis (Y12), Critical Paths Tagged With: Band 4, smc-6916-10-Precedence Tables, smc-6916-20-Forward Scanning, smc-916-10-Table to Network, smc-916-20-Forward Scanning

Networks, STD2 N3 EQ-Bank 32

An engineering project requires activities `A` to `G` to be completed, as shown in the table.
 


 

The minimum completion time for the project is 25 days and the critical path includes activities `B, D, E` and `F`. The float for activity `G` is two days and the float for activity `C` is four days.

Find the possible duration for each of the activities `A, C, F` and `G`. Include a network diagram in your answer.   (5 marks)

Show Answers Only

`text(Duration of)\ F = 1\ text(day)`

`text(Duration of)\ G = 4\ text(days)`

`text(*Understand why there are many possibilities for the duration of)`

`A and C, text(provided they add up to 20 days and)\ A\ text(is not longer)`

`text{than 7 days (or a new critical path is created)}.`

Show Worked Solution

`text(Sketch the network:)`
 

`text{Critical path information included in the network (where EST = LST)}`

`F\ text(is on critical path)rightarrow text(no float)`

`:.\ text(Duration of)\ F=  25-24 = 1\ text(day)`

 

`text(Duration of)\ G` `=\ text(LST of next activity − EST of)\ G-text(float)`
  `= 25-19-2= 4\ text(days)`

 

`text(The float of)\ C\ text{is 4 days (given)}`

`:.\ text(Duration of)\ C` `=\ text(LST of)\ F-text(EST of)\ C-4`
  `= 24-text(EST of)\ C-4`
  `= 20-text(EST of)\ C`

 

`text(EST of)\ C =\ text(Duration of)\ A\ \ (A\ text(has no prerequisites))`

`=>\ text(Duration of)\ A +\ text(Duration of)\ C = 20\ text(days)`

`:.\ text(Possible durations of)\ A\ text(and)\ C\ text(are:)`

`A = 5\ text(days), C = 15\ text(days)`
 

`text(*Understand why there are many possibilities for the duration of)`

`A and C, text(provided they add up to 20 days and)\ A\ text(is not longer)`

`text{than 7 days (or a new critical path is created)}.`

Filed Under: Critical Path Analysis (Y12), Critical Paths Tagged With: Band 5, smc-6916-10-Precedence Tables, smc-6916-30-Scanning Both Ways, smc-6916-50-Dummy Activity, smc-916-10-Table to Network, smc-916-30-Scanning Both Ways, smc-916-50-Dummy Activity

Networks, STD2 N3 EQ-Bank 31

An engineering project requires activities `A` to `G` to be completed, as shown in the table.
 


 

The minimum completion time for the project is 40 weeks and the critical path includes activities `A, C, E` and `G`. The float for activity `F` is six weeks and the float for activity `D` is 9 weeks.

Find the possible duration for each of the activities `B, D, F` and `G`. Include a network diagram in your answer.   (5 marks)

Show Answers Only


 

`text(Duration of)\ G = 3\ text(weeks)`

`text(Duration of)\ F = 9\ text(weeks)`

`text(There are many possibilities for the duration of)\ B and D`

`text(provided they add up to 28 weeks and)\ B\ text(is not longer)`

`text{than 10 weeks (new critical path)}.`

Show Worked Solution

`text(Sketch network:)`

`text{Critical path added to network (where EST = LST)}`

`G\ text(is on critical path ⇒ no float)`

`:.\ text(Duration of)\ G = 40-37 = 3\ text(weeks)`

 

`text(Duration of)\ F` `=40- text(EST of)\ F-text(float)`
  `= 40-25-6= 9\ text(weeks)`

 

`text(Float of)\ D = 9\ text{weeks (given)}`

`:.\ text(Duration of)\ D` `=\ text(LST of)\ G-\ text(EST of)\ D-9`
  `= 37-\ text(EST of)\ D-9`
  `= 28-\ text(EST of)\ D`

 

`text(EST of)\ D =\ text(Duration of)\ B\ \ \ (B\ text(has no prerequisites))`

`text(Duration of)\ B +\ text(Duration of)\ D = 28\ text(weeks)`

`:.\ text(Possible durations of)\ B\ text(and)\ D\ text(are:)`

`B = 1\ text(week), D = 27\ text(weeks)`

 

`text(*Understand why there are many possibilities for the duration of)`

`B and D, text(provided they add up to 28 weeks and)\ B\ text(is not longer)`

`text{than 10 weeks (or a new critical path is created)}.`

Filed Under: Critical Path Analysis (Y12), Critical Paths Tagged With: Band 5, smc-6916-10-Precedence Tables, smc-6916-30-Scanning Both Ways, smc-6916-50-Dummy Activity, smc-916-10-Table to Network, smc-916-30-Scanning Both Ways, smc-916-50-Dummy Activity

Networks, STD2 N3 2012 FUR1 8 MC

networks-fur1-2012-vcaa-8-mc 
 

Eight activities, `A, B, C, D, E, F, G`  and  `H`, must be completed for a project.

The network above shows these activities and their usual duration in hours.

The duration of each activity can be reduced by one hour.

To complete this project in 16 hours, the minimum number of activities that must be reduced by one hour each is

  1. `1`
  2. `2`
  3. `3`
  4. `4`
Show Answers Only

`C`

Show Worked Solution

`text(Two critical paths)\ AFH\ text(and)\ BCFH => 18\ text(hours)`

♦♦ Mean mark 30%.

`text(Paths)\ AEG\ text(and)\ BCEG => 17\ text(hours)`

`text(Reducing)\ A\ text(and)\ B\ text(by 1 hour each reduces each)`

`text(path above by 1 hour.)`

 

`text(Need to reduce)\ AFH\ text(and)\ BCFH\ text(by 1 hour to 16 hours.)`

`=>\ text(Reducing either)\ F\ text(or)\ H\ text(by 1 hour brings the)`

`text(critical path down to 16 hours.)`

`=> C`

Filed Under: Critical Path Analysis (Y12), Critical Paths Tagged With: Band 6, smc-6916-20-Forward Scanning, smc-916-20-Forward Scanning

Networks, STD2 N3 2007 FUR2 4

A community centre is to be built on the new housing estate.

Nine activities have been identified for this building project.

The directed network below shows the activities and their completion times in weeks.

 

  1. Determine the minimum time, in weeks, to complete this project.   (1 mark)

    --- 1 WORK AREA LINES (style=lined) ---

  2. Determine the float time, in weeks, for activity `D`.   (2 marks)

    --- 4 WORK AREA LINES (style=lined) ---

The builders of the community centre are able to speed up the project.

Some of the activities can be reduced in time at an additional cost.

The activities that can be reduced in time are `A, C, F, E` and `G`.

  1. Which of these activities, if reduced in time individually, would not result in an earlier completion of the project?   (1 mark)

    --- 2 WORK AREA LINES (style=lined) ---

The owner of the estate is prepared to pay the additional cost to achieve early completion.

The cost of reducing the time of each activity is $5000 per week.

The maximum reduction in time for each one of the five activities, `A, C, E, F, G`, is 2 weeks.

  1. Determine the minimum time, in weeks, for the project to be completed now that certain activities can be reduced in time.   (1 mark)

    --- 1 WORK AREA LINES (style=lined) ---

  2. Determine the minimum additional cost of completing the project in this reduced time.   (1 mark)

    --- 1 WORK AREA LINES (style=lined) ---

Show Answers Only

a.   `19\ text(weeks)`

b.    `5\ text(weeks)`

c.    `A, E, G`

d.    `text(15 weeks)`

e.    `$25\ 000`

Show Worked Solution

a.    `text(Scanning forwards and backwards:)`
 

 
`BCFHI\ \ text(is the critical path.)`

♦ Mean mark of all parts (combined) 40%.

`:.\ text(Minimum time)= 4 + 3 + 4 + 2 + 6= 19\ text(weeks)`

  
b.    `text(EST of)\ D=4`

`text(LST of)\ D=9`

`:.\ text(Float time of)\ D= 9-4= 5\ text(weeks)`
  

c.    `A, E,\ text(and)\ G\ text(are not currently on the critical path,)`

`text(therefore reducing their time will not result in an)`

`text(earlier completion time.)`
 

d.    `text(Reduce)\ C\ text(and)\ F\ text(by 2 weeks each.)`

`text(However, a new critical path created:)\ BEHI\ \ text{(16 weeks)}`

`:.\ text(Also reduce)\ E\ text(by 1 week.)`

`:.\ text(Minimum completion time = 15 weeks)`

  
e.    `text(Additional cost)= 5 xx $5000= $25\ 000`

Filed Under: Critical Path Analysis (Y12), Critical Paths Tagged With: Band 4, Band 5, Band 6, smc-6916-30-Scanning Both Ways, smc-916-30-Scanning Both Ways

Networks, STD2 N3 2006 FUR2 3

The five musicians are to record an album. This will involve nine activities.

The activities and their immediate predecessors are shown in the following table.

The duration of each activity is not yet known.
 

NETWORKS, FUR2 2006 VCAA 31
 

  1. Use the information in the table above to complete the network below by including activities `G`, `H` and `I`.   (2 marks)
     

NETWORKS, FUR2 2006 VCAA 32
 

There is only one critical path for this project.

  1. How many non-critical activities are there?   (1 mark)

    --- 1 WORK AREA LINES (style=lined) ---

The following table gives the earliest start times (EST) and latest start times (LST) for three of the activities only. All times are in hours.


Networks, FUR2 2006 VCAA 3_3

  1. Write down the critical path for this project.   (1 mark)

    --- 1 WORK AREA LINES (style=lined) ---

The minimum time required for this project to be completed is 19 hours.

  1. What is the duration of activity `I`?   (1 mark)

The duration of activity `C` is 3 hours.

--- 1 WORK AREA LINES (style=lined) ---

  1. Determine the maximum combined duration of activities ` F` and `H`.   (1 mark) 

    --- 1 WORK AREA LINES (style=lined) ---

Show Answers Only

a. 

networks-fur2-2006-vcaa-3-answer

b.    `5`

c.    `B E G I`

d.    `text(7 hours)`

e.    `text(8 hours)`

Show Worked Solution
a.     networks-fur2-2006-vcaa-3-answer

 

b.    `text(S)text(ince no time information, possible critical paths are:)`

`ADGI, BEGI\ text(or)\ CFHI\ \ text{(all have 4 activities)}`
 

`:.\ text(Non-critical activities)= 9-4 = 5`

 

c.    `text(Critical activities have zero float time.)`

♦ Mean mark of parts (c)-(e) (combined) was 36%.

`=> A\ text(and)\ C\ text(are non-critical.)`

`:. B E G I\ text(is the critical path.)`
  

d.    `text(Duration of)\ \ I= 19-12= 7\ text(hours)`
  

e.   `text(Maximum time for)\ F\ text(and)\ H`

♦♦ MARKER’S COMMENT: Many students incorrectly answered 9 hours in part (e).

`=\ text(LST of)\ I–text(duration)\ C – text(slack time of)\ C`

`= 12-3-1= 8\ text(hours)`

Filed Under: Critical Path Analysis (Y12), Critical Paths Tagged With: Band 4, Band 5, smc-6916-10-Precedence Tables, smc-916-10-Table to Network

Networks, STD2 N3 2011 FUR1 7 MC

Andy, Brian and Caleb must complete three activities in total (K, L and M)

The table shows the person selected to complete each activity, the time it will take to complete the activity in minutes and the immediate predecessor for each activity.
 

\begin{array}{|l|c|c|c|}
\hline
\textbf{Person} & \textbf{Activity} & \textbf{Duration} & \textbf{Immediate predecessor} \\
\hline
\text{Andy} & K & 13 & - \\
\hline
\text{Brian} & L & 5 & K \\
\hline
\text{Caleb} & M & 16 & L \\
\hline
\end{array}

 
All three activities must be completed in a total of 40 minutes.

The instant that Andy starts his activity, Caleb gets a telephone call.

The maximum time, in minutes, that Caleb can speak on the telephone before he must start his allocated activity is

  1. `5`
  2. `13`
  3. `18`
  4. `24`
Show Answers Only

`D`

Show Worked Solution

`text(Maximum speaking time on phone)`

♦♦ Mean mark 33%.
MARKER’S COMMENT: Many students incorrectly answered the earliest starting time, C.

`= 40-text(duration of)\ M`

`= 40-16= 24\ text(minutes)`

`=>  D`

Filed Under: Critical Path Analysis (Y12), Critical Paths Tagged With: Band 5, smc-6916-10-Precedence Tables, smc-916-10-Table to Network

Networks, STD2 N3 2006 FUR1 9 MC

The network below shows the activities and their completion times (in hours) that are needed to complete a project.
 


 

The project is to be optimised by reducing the completion time of one activity only.

This will reduce the completion time of the project by a maximum of

  1. 1 hour 
  2. 3 hours
  3. 4 hours
  4. 5 hours
Show Answers Only

`C`

Show Worked Solution

`text(Scanning forward:)`
 


 

`text(Critical path:)`

♦♦♦ Mean mark 17%.
MARKER’S COMMENT: When choosing an activity to crash, take care that a new critical path is not created.

`=> BDCEHJ\ text{(19 hours)}`
 

`text(Other routes not through)\ B,`

`ACEHJ\ text{(15 hours),}\ AFJ\ text{(14 hours)}`
 

`:.\ text(Activity)\ B\ text(could be reduced by 4 hours without)`

`text(a new critical path emerging.)`
 

`=> C`

Filed Under: Critical Path Analysis (Y12), Critical Paths Tagged With: Band 6, smc-6916-20-Forward Scanning, smc-6916-50-Dummy Activity, smc-916-20-Forward Scanning, smc-916-50-Dummy Activity

Networks, STD2 N3 2014 FUR1 8 MC

Which one of the following statements about critical paths is true?

  1. There can be only one critical path in a project.
  2. A critical path will always include the activity that takes the longest time to complete.
  3. Reducing the time of any activity on a critical path for a project will always reduce the minimum completion time for the project.
  4. If there are no other changes, increasing the time of any activity on a critical path will always increase the completion time of a project.
Show Answers Only

`D`

Show Worked Solution

`text(If any activity on a critical path takes longer, the project)`

♦ Mean mark 40%.

`text{completion time increases by the equivalent amount}`

`text{of time (although the reverse is not true).}`

`=>  D` 

Filed Under: Critical Path Analysis (Y12), Critical Paths Tagged With: Band 5, smc-6916-40-Critical Path Adjustments, smc-916-40-Critical Path Adjustments

Networks, STD2 N3 2015 FUR1 9 MC

The table below shows, in minutes, the duration, the earliest starting time (EST) and the latest starting time (LST) of eight activities needed to complete a project.
 

NETWORKS, FUR1 2015 VCAA 9 MC

 
Which one of the following directed graphs shows the sequence of these activities?

A.
B.
C.
D.
Show Answers Only

`B`

Show Worked Solution

`text(Consider option)\ B,`

`text(Scanning forwards:)`
  


 

`text(This network matches the table information.)`

`=> B`

Filed Under: Critical Path Analysis (Y12), Critical Paths Tagged With: Band 4, smc-6916-10-Precedence Tables, smc-916-10-Table to Network