The directed network shows the sequence of activities required to complete a project.
The time to complete each activity, in hours, is also shown.
What is the earliest starting time (EST) in hours for activity \(K\)?
- 10
- 11
- 12
- 13
Aussie Maths & Science Teachers: Save your time with SmarterEd
The directed network shows the sequence of activities required to complete a project.
The time to complete each activity, in hours, is also shown.
What is the earliest starting time (EST) in hours for activity \(K\)?
\(C\)
\(\text{EST}(K)\ \text{occurs when all possible activities before it are complete.}\)
\(\text{There are three possible routes to get to}\ K.\)
| \(\text{EST}(K)\) | \(=\max(4+3+5,\ \ 4+6+1,\ \ 4+3+2+1)\) |
| \(=\max(12,11,10)\) | |
| \(=12\ \text{hours}\) |
\(\Rightarrow C\)
Lena is opening a new café. The project requires the completion of 7 activities, \(A\) to \(G\). The project is due to be completed in 15 days.
The directed network diagram shows these activities with their completion times in days.
--- 0 WORK AREA LINES (style=lined) ---
--- 3 WORK AREA LINES (style=lined) ---
a.
b. \(B\text{, }D\text{ and }E\)
a.
b. \(\text{By inspection of the Gantt chart.}\)
\(\text{Activities which could be occurring at }\approx 6.5\ \text{on chart (midday day 7):}\)
\(B\text{, }D\text{ and }E\)
A project requires the completion of 8 activities, \(A\) to \(H\). The project is due to be completed in 16 days.
The directed network diagram shows these activities with their completion times in days.
--- 0 WORK AREA LINES (style=lined) ---
--- 3 WORK AREA LINES (style=lined) ---
a.
b. \(C, D\ \text{and}\ F\)
a.
b. \(\text{By inspection of the Gantt chart.}\)
\(\text{Activities which could be occurring at}\ \approx 8.5\ \text{on chart (midday day 9):}\)
\(C, D\ \text{and}\ F\)
The Gantt chart below shows the activities involved in organising a school sports carnival.
Which activity has the greatest float time?
\(B\)
\(\text{From the Gantt chart, the dashed extensions show:}\)
\(\text{B: float = 3 hours}\)
\(\text{D: float = 5 hours}\)
\(\text{E: float = 3 hours}\)
\(\text{G: float = 0 (critical path, no dashed extension)}\)
\(\text{Activity D has the greatest float time (5 hours).}\)
\(\Rightarrow B\)
The Gantt chart below shows the activities involved in organising a community market day. Critical path activities are shown as solid bars and non-critical activities show available float as dashed extensions.
Activity \(D\) is delayed by 7 hours and activity \(B\) is delayed by 1 hour. What is the new minimum completion time for the project?
\(C\)
\(\text{From the Gantt chart:}\)
\(\text{D has float of 5 hours. Delay of 7 exceeds float by 2.}\)
\(\text{B has float of 3 hours. Delay of 1 is within float.}\)
\(\text{Only the delay to D affects completion time.}\)
\(\text{New minimum} = 14+2 = 16 \text{ hours}\)
\(\Rightarrow C\)
The construction of a new reptile exhibit is a project involving nine activities, \(A\) to \(I\). The network diagram below shows the activities and their completion times in weeks. Some values are missing.
The Gantt chart below has been created for this project.
--- 2 WORK AREA LINES (style=lined) ---
--- 4 WORK AREA LINES (style=lined) ---
--- 5 WORK AREA LINES (style=lined) ---
a. \(ACDFGI\)
b. \(\text{B} = 5 \text{ weeks, H} = 7 \text{ weeks}\)
c. \(\text{From the Gantt chart, activity E has a float of 6 weeks (see the dashed}\)
\(\text{extension from week 10 to 16).}\)
\(\text{The delay of 8 weeks exceeds the float of 6 weeks.}\)
\(\text{The project will be delayed by } 8-6 = 2 \text{ weeks.}\)
\(\text{New minimum completion time} = 25+2 = 27 \text{ weeks.}\)
a. \(\text{The critical path is the continuous solid bar on row 1 of the Gantt chart.}\)
\(\text{Critical path:}\ ACDFGI\)
b. \(\text{Activities B and H are not labelled in the network diagram.}\)
\(\text{From the Gantt chart:}\)
\(\text{B starts at week 0, ends at week 5} \to \text{duration} = 5 \text{ weeks}\)
\(\text{H starts at week 13, ends at week 20} \to \text{duration} = 7 \text{ weeks}\)
c. \(\text{From the Gantt chart, activity E has a float of 6 weeks (see the dashed}\)
\(\text{extension from week 10 to 16).}\)
\(\text{The delay of 8 weeks exceeds the float of 6 weeks.}\)
\(\text{The project will be delayed by } 8-6 = 2 \text{ weeks.}\)
\(\text{New minimum completion time} = 25+2 = 27 \text{ weeks.}\)
A Gantt chart for a project with activities \(A, B, C, D, E, F, G\) and \(H\) has been created where all times are in hours. The Gantt chart can be used to complete the missing information on the edges in the network diagram.
--- 3 WORK AREA LINES (style=lined) ---
--- 2 WORK AREA LINES (style=lined) ---
a. \(\text{C} = 4 \text{ hours, D} = 5 \text{ hours, E} = 7 \text{ hours}\)
b. \(26 \text{ hours}\)
a. \(\text{Using the Gantt chart}\)
\(\text{C (between A and F):} \)
\(\Rightarrow\ \text{Starts hour 7, ends hour 11 = 4 hours duration}\)
\(\text{D (between B and G):}\)
\(\Rightarrow\ \text{Starts hour 3, ends hour 9 = 6 hours duration}\)
\(\text{E (between B and H):}\)
\(\Rightarrow\ \text{Starts hour 3, ends hour 13 = 10 hours duration}\)
b. \(\text{From the Gantt chart, the project ends at hour 26.}\)
\(\text{Minimum completion time} = 26 \text{ hours}\)
A project requires the completion of 9 activities, \(A\) to \(I\). The project is due to be completed in 13 days.
The directed network diagram shows these activities with their completion times in days.
--- 0 WORK AREA LINES (style=lined) ---
--- 3 WORK AREA LINES (style=lined) ---
The activities and corresponding durations in days for a project are shown in the network diagram.
\begin{array} {|c|c|}
\hline
\rule{0pt}{2.5ex} \text{Activity} \rule[-1ex]{0pt}{0pt} & \text{Immediate prerequisite(s)} \\
\hline
\rule{0pt}{2.5ex} B \rule[-1ex]{0pt}{0pt} & \\
\hline
\rule{0pt}{2.5ex} E \rule[-1ex]{0pt}{0pt} & \\
\hline
\rule{0pt}{2.5ex} F \rule[-1ex]{0pt}{0pt} & \\
\hline
\end{array}
--- 4 WORK AREA LINES (style=lined) ---
The duration of activity \( A \) is increased by 2. Does this affect the critical path for the project? Give a reason for your answer. (1 mark)
--- 4 WORK AREA LINES (style=lined) ---
a.
\begin{array} {|c|c|}
\hline
\rule{0pt}{2.5ex} \text{Activity} \rule[-1ex]{0pt}{0pt} & \text{Immediate prerequisite(s)} \\
\hline
\rule{0pt}{2.5ex} B \rule[-1ex]{0pt}{0pt} & \text{X} \\
\hline
\rule{0pt}{2.5ex} E \rule[-1ex]{0pt}{0pt} & C,D \\
\hline
\rule{0pt}{2.5ex} F \rule[-1ex]{0pt}{0pt} & E \\
\hline
\end{array}
b. \(\text{Critical Path:}\ BDEFH\)
\(\text{Minimum Duration}\ =4+5+5+7+5=26\ \text{days}\)
c. \(\text{If duration of activity \(A\) is increased by 2:}\)
\(\text{The critical path remains unchanged (EST of activity \(E\) remains = 9)}\)
a.
\begin{array} {|c|c|}
\hline
\rule{0pt}{2.5ex} \text{Activity} \rule[-1ex]{0pt}{0pt} & \text{Immediate prerequisite(s)} \\
\hline
\rule{0pt}{2.5ex} B \rule[-1ex]{0pt}{0pt} & \text{X} \\
\hline
\rule{0pt}{2.5ex} E \rule[-1ex]{0pt}{0pt} & C,D \\
\hline
\rule{0pt}{2.5ex} F \rule[-1ex]{0pt}{0pt} & E \\
\hline
\end{array}
b.
\(\text{Critical Path:}\ BDEFH\)
\(\text{Minimum Duration}\ =4+5+5+7+5=26\ \text{days}\)
c. \(\text{If duration of activity \(A\) is increased by 2:}\)
\(\text{The critical path remains unchanged (EST of activity \(E\) remains = 9)}\)
A project involving nine activities is shown in the network diagram.
The duration of each activity is not yet known.
The following table gives the earliest start time (EST) and latest start time (LST) for three of the activities. All times are in hours.
\begin{array} {|c|c|c|}
\hline
\rule{0pt}{2.5ex} \textit{Activity} \rule[-1ex]{0pt}{0pt} & EST & LST \\
\hline
\rule{0pt}{2.5ex} A \rule[-1ex]{0pt}{0pt} & \ \ \ \ \ \ 0\ \ \ \ \ \ & \ \ \ \ \ \ 2\ \ \ \ \ \ \\
\hline
\rule{0pt}{2.5ex} C \rule[-1ex]{0pt}{0pt} & 0 & 1 \\
\hline
\rule{0pt}{2.5ex} I \rule[-1ex]{0pt}{0pt} & 12 & 12 \\
\hline
\end{array}
--- 2 WORK AREA LINES (style=lined) ---
--- 2 WORK AREA LINES (style=lined) ---
--- 2 WORK AREA LINES (style=lined) ---
a. \(\text{Critical Path:}\ BEGI\)
b. \(\text{Duration of}\ I =7\ \text{hours}\)
c. \(\text{Max time}\ =8\ \text{hours}\)
a. \(\text{Activity}\ A\ \text{and}\ C: \ LST \gt EST\)
\(\Rightarrow\ \text{Activity}\ A\ \text{and}\ C\ \text{not on critical path.}\)
\(\text{Critical Path:}\ BEGI\)
b. \(\text{Duration of}\ I = 19-12=7\ \text{hours}\)
c. \(\text{Since}\ C + F + H + I\ \text{is not a critical path:}\)
\(C + F + H + I = 18\ \text{or less (C.P. = 19 hours)}\)
\(3+F+H+7 = 18\ \text{or less}\)
\(\Rightarrow\ F+H = 8\ \text{or less}\)
\(\therefore\ \text{Max time from start of}\ F\ \text{to end of}\ H = 8\ \text{hours}\)
A function centre employs staff so that all necessary tasks can be completed between the end of one function and the beginning of the next function. The network diagram shows the time taken in hours for the tasks that need to be completed. --- 4 WORK AREA LINES (style=lined) --- --- 4 WORK AREA LINES (style=lined) --- a. `HIGC and HIK` b. `text{More staff should be hired for task}\ I.` `text{By decreasing task}\ I\ text{by 3 hours (so it takes 4 hours), the}` `text{critical path of the network reduces to 14 hours.}`
The network diagram shows the time needed for each step in order to complete a project.
What is the critical path to complete the project?
`B`
`text{Critical Path:}\ ADG`
`=>B`
The directed graph below shows the sequence of activities required to complete a project.
The time taken to complete each activity, in hours, is also shown.
The minimum completion time for this project is 18 hours.
The time taken to complete activity `E` is labelled `x`.
What is the maximum value of `x`? (2 marks)
--- 4 WORK AREA LINES (style=lined) ---
`text(3 hours)`
`text{Consider all possible network paths:}`
`ADHJ \ -> \ text{18 hours}`
`BEJ \ -> \ (12 + x) \ text{hours}`
`CGFEJ \ -> \ (15 + x) \ text{hours}`
`CGIJ \ -> \ text{18 hours}`
`text{Minimum completion time = 18 hours}`
`=>\ text{No path can be longer than 18 hours}`
`:. \ x_text{max} = 3 \ text{hours}`
A project requires completion of 11 tasks `A, B, C, . . . , K.`
A network diagram for the project giving the completion time for each task, in minutes, is shown.
--- 1 WORK AREA LINES (style=lined) ---
--- 2 WORK AREA LINES (style=lined) ---
--- 4 WORK AREA LINES (style=lined) ---
a. `40 \ text{minutes}`
b. `A – C – D – E – G – J – K`
c. `text{Float time = 1minute}`
The preparation of a meal requires the completion of all activities `A` to `J`. The network diagram shows the activities and their completion times in minutes.
--- 1 WORK AREA LINES (style=lined) ---
--- 5 WORK AREA LINES (style=lined) ---
--- 0 WORK AREA LINES (style=lined) ---
The construction of the new reptile exhibit is a project involving nine activities, `A` to `I`.
The directed network below shows these activities and their completion times in weeks.
--- 1 WORK AREA LINES (style=lined) ---
--- 1 WORK AREA LINES (style=lined) ---
--- 2 WORK AREA LINES (style=lined) ---
a. `D, G and I`
b. `text(See Worked Solutions)`
c. `2\ text(weeks)`
a. `D, G and I`
b. `text(Scanning forwards and backwards:)`
`text(Critical Path:)\ ACDFGI`
c. `text{LST (activity}\ B text{)}=7-5=2\ text(weeks)`
A project involves nine activities, `A` to `I`.
The immediate predecessor(s) of each activity is shown in the table below.
\begin{array} {|c|c|}
\hline \ \ \textbf{Activity}\ \ & \textbf{Immediate} \\ & \textbf{predecessor(s)} \\
\hline \rule{0pt}{2.5ex} A \rule[-1ex]{0pt}{0pt} & - \\
\hline \rule{0pt}{2.5ex} B \rule[-1ex]{0pt}{0pt} & A \\
\hline \rule{0pt}{2.5ex} C \rule[-1ex]{0pt}{0pt} & A \\
\hline \rule{0pt}{2.5ex} D \rule[-1ex]{0pt}{0pt} & B \\
\hline \rule{0pt}{2.5ex} E \rule[-1ex]{0pt}{0pt} & B, C \\
\hline \rule{0pt}{2.5ex} F \rule[-1ex]{0pt}{0pt} & D \\
\hline \rule{0pt}{2.5ex} G \rule[-1ex]{0pt}{0pt} & D \\
\hline \rule{0pt}{2.5ex} H \rule[-1ex]{0pt}{0pt} & E, F \\
\hline \rule{0pt}{2.5ex} I \rule[-1ex]{0pt}{0pt} & G, H \\
\hline \end{array}
A directed network for this project will require a dummy activity.
Sketch the network diagram, clearly identifying the dummy activity. (3 marks)
A project requires activities `A` to `F` to be completed. The activity chart shows the immediate prerequisite(s) and duration for each activity.
--- 8 WORK AREA LINES (style=lined) ---
--- 2 WORK AREA LINES (style=lined) ---
a. `text(15 hours)`
b. `text(3 hours)`
| a. |
`text(Scanning forwards:)`
`text(Minimum time = 2 + 6 + 2 + 4 + 1 = 15 hours)`
`text{(Scanning forwards and backwards is highly recommended but not}`
`text{required in the network diagram.)}`
b. `text(Critical Path is)\ ABDEF.`
`text(Non-critical activity is)\ C.`
`text(Float time)=5-2=3\ text(hours)`
A project requires nine activities (A–I) to be completed. The duration, in hours, and the immediate predecessor(s) of each activity are shown in the table below.
--- 7 WORK AREA LINES (style=lined) ---
--- 4 WORK AREA LINES (style=lined) ---
An engineering project requires activities `A` to `G` to be completed, as shown in the table.
The minimum completion time for the project is 25 days and the critical path includes activities `B, D, E` and `F`. The float for activity `G` is two days and the float for activity `C` is four days.
Find the possible duration for each of the activities `A, C, F` and `G`. Include a network diagram in your answer. (5 marks)
`text(Sketch the network:)`
`text{Critical path information included in the network (where EST = LST)}`
`F\ text(is on critical path)rightarrow text(no float)`
`:.\ text(Duration of)\ F= 25-24 = 1\ text(day)`
| `text(Duration of)\ G` | `=\ text(LST of next activity − EST of)\ G-text(float)` |
| `= 25-19-2= 4\ text(days)` |
`text(The float of)\ C\ text{is 4 days (given)}`
| `:.\ text(Duration of)\ C` | `=\ text(LST of)\ F-text(EST of)\ C-4` |
| `= 24-text(EST of)\ C-4` | |
| `= 20-text(EST of)\ C` |
`text(EST of)\ C =\ text(Duration of)\ A\ \ (A\ text(has no prerequisites))`
`=>\ text(Duration of)\ A +\ text(Duration of)\ C = 20\ text(days)`
`:.\ text(Possible durations of)\ A\ text(and)\ C\ text(are:)`
`A = 5\ text(days), C = 15\ text(days)`
`text(*Understand why there are many possibilities for the duration of)`
`A and C, text(provided they add up to 20 days and)\ A\ text(is not longer)`
`text{than 7 days (or a new critical path is created)}.`
An engineering project requires activities `A` to `G` to be completed, as shown in the table.
The minimum completion time for the project is 40 weeks and the critical path includes activities `A, C, E` and `G`. The float for activity `F` is six weeks and the float for activity `D` is 9 weeks.
Find the possible duration for each of the activities `B, D, F` and `G`. Include a network diagram in your answer. (5 marks)
`text(Sketch network:)`
`text{Critical path added to network (where EST = LST)}`
`G\ text(is on critical path ⇒ no float)`
`:.\ text(Duration of)\ G = 40-37 = 3\ text(weeks)`
| `text(Duration of)\ F` | `=40- text(EST of)\ F-text(float)` |
| `= 40-25-6= 9\ text(weeks)` |
`text(Float of)\ D = 9\ text{weeks (given)}`
| `:.\ text(Duration of)\ D` | `=\ text(LST of)\ G-\ text(EST of)\ D-9` |
| `= 37-\ text(EST of)\ D-9` | |
| `= 28-\ text(EST of)\ D` |
`text(EST of)\ D =\ text(Duration of)\ B\ \ \ (B\ text(has no prerequisites))`
`text(Duration of)\ B +\ text(Duration of)\ D = 28\ text(weeks)`
`:.\ text(Possible durations of)\ B\ text(and)\ D\ text(are:)`
`B = 1\ text(week), D = 27\ text(weeks)`
`text(*Understand why there are many possibilities for the duration of)`
`B and D, text(provided they add up to 28 weeks and)\ B\ text(is not longer)`
`text{than 10 weeks (or a new critical path is created)}.`
Eight activities, `A, B, C, D, E, F, G` and `H`, must be completed for a project.
The network above shows these activities and their usual duration in hours.
The duration of each activity can be reduced by one hour.
To complete this project in 16 hours, the minimum number of activities that must be reduced by one hour each is
`C`
`text(Two critical paths)\ AFH\ text(and)\ BCFH => 18\ text(hours)`
`text(Paths)\ AEG\ text(and)\ BCEG => 17\ text(hours)`
`text(Reducing)\ A\ text(and)\ B\ text(by 1 hour each reduces each)`
`text(path above by 1 hour.)`
`text(Need to reduce)\ AFH\ text(and)\ BCFH\ text(by 1 hour to 16 hours.)`
`=>\ text(Reducing either)\ F\ text(or)\ H\ text(by 1 hour brings the)`
`text(critical path down to 16 hours.)`
`=> C`
A community centre is to be built on the new housing estate.
Nine activities have been identified for this building project.
The directed network below shows the activities and their completion times in weeks.
--- 1 WORK AREA LINES (style=lined) ---
--- 4 WORK AREA LINES (style=lined) ---
The builders of the community centre are able to speed up the project.
Some of the activities can be reduced in time at an additional cost.
The activities that can be reduced in time are `A, C, F, E` and `G`.
--- 2 WORK AREA LINES (style=lined) ---
The owner of the estate is prepared to pay the additional cost to achieve early completion.
The cost of reducing the time of each activity is $5000 per week.
The maximum reduction in time for each one of the five activities, `A, C, E, F, G`, is 2 weeks.
--- 1 WORK AREA LINES (style=lined) ---
--- 1 WORK AREA LINES (style=lined) ---
a. `19\ text(weeks)`
b. `5\ text(weeks)`
c. `A, E, G`
d. `text(15 weeks)`
e. `$25\ 000`
a. `text(Scanning forwards and backwards:)`
`BCFHI\ \ text(is the critical path.)`
`:.\ text(Minimum time)= 4 + 3 + 4 + 2 + 6= 19\ text(weeks)`
b. `text(EST of)\ D=4`
`text(LST of)\ D=9`
`:.\ text(Float time of)\ D= 9-4= 5\ text(weeks)`
c. `A, E,\ text(and)\ G\ text(are not currently on the critical path,)`
`text(therefore reducing their time will not result in an)`
`text(earlier completion time.)`
d. `text(Reduce)\ C\ text(and)\ F\ text(by 2 weeks each.)`
`text(However, a new critical path created:)\ BEHI\ \ text{(16 weeks)}`
`:.\ text(Also reduce)\ E\ text(by 1 week.)`
`:.\ text(Minimum completion time = 15 weeks)`
e. `text(Additional cost)= 5 xx $5000= $25\ 000`
The five musicians are to record an album. This will involve nine activities.
The activities and their immediate predecessors are shown in the following table.
The duration of each activity is not yet known.
There is only one critical path for this project.
--- 1 WORK AREA LINES (style=lined) ---
The following table gives the earliest start times (EST) and latest start times (LST) for three of the activities only. All times are in hours.
--- 1 WORK AREA LINES (style=lined) ---
The minimum time required for this project to be completed is 19 hours.
The duration of activity `C` is 3 hours.
--- 1 WORK AREA LINES (style=lined) ---
--- 1 WORK AREA LINES (style=lined) ---
| a. | ![]() |
b. `text(S)text(ince no time information, possible critical paths are:)`
`ADGI, BEGI\ text(or)\ CFHI\ \ text{(all have 4 activities)}`
`:.\ text(Non-critical activities)= 9-4 = 5`
c. `text(Critical activities have zero float time.)`
`=> A\ text(and)\ C\ text(are non-critical.)`
`:. B E G I\ text(is the critical path.)`
d. `text(Duration of)\ \ I= 19-12= 7\ text(hours)`
e. `text(Maximum time for)\ F\ text(and)\ H`
`=\ text(LST of)\ I–text(duration)\ C – text(slack time of)\ C`
`= 12-3-1= 8\ text(hours)`
Andy, Brian and Caleb must complete three activities in total (K, L and M)
The table shows the person selected to complete each activity, the time it will take to complete the activity in minutes and the immediate predecessor for each activity.
\begin{array}{|l|c|c|c|}
\hline
\textbf{Person} & \textbf{Activity} & \textbf{Duration} & \textbf{Immediate predecessor} \\
\hline
\text{Andy} & K & 13 & - \\
\hline
\text{Brian} & L & 5 & K \\
\hline
\text{Caleb} & M & 16 & L \\
\hline
\end{array}
All three activities must be completed in a total of 40 minutes.
The instant that Andy starts his activity, Caleb gets a telephone call.
The maximum time, in minutes, that Caleb can speak on the telephone before he must start his allocated activity is
`D`
`text(Maximum speaking time on phone)`
`= 40-text(duration of)\ M`
`= 40-16= 24\ text(minutes)`
`=> D`
The network below shows the activities and their completion times (in hours) that are needed to complete a project.
The project is to be optimised by reducing the completion time of one activity only.
This will reduce the completion time of the project by a maximum of
`C`
`text(Scanning forward:)`
`text(Critical path:)`
`=> BDCEHJ\ text{(19 hours)}`
`text(Other routes not through)\ B,`
`ACEHJ\ text{(15 hours),}\ AFJ\ text{(14 hours)}`
`:.\ text(Activity)\ B\ text(could be reduced by 4 hours without)`
`text(a new critical path emerging.)`
`=> C`
Which one of the following statements about critical paths is true?
`D`
`text(If any activity on a critical path takes longer, the project)`
`text{completion time increases by the equivalent amount}`
`text{of time (although the reverse is not true).}`
`=> D`
The table below shows, in minutes, the duration, the earliest starting time (EST) and the latest starting time (LST) of eight activities needed to complete a project.
Which one of the following directed graphs shows the sequence of these activities?
| A. | ![]() |
| B. | ![]() |
| C. | ![]() |
| D. | ![]() |
`B`