The network diagram shows the time needed for each step in order to complete a project.
 

   

What is the float time of activity \(E\)?

  1. 2
  2. 5
  3. 7
  4. 9
Show Answers Only

\(B\)

Show Worked Solution

\(\text{Float time} = LST\ (\text{activity}\ E)-EST\ (\text{activity}\ E)=7-2=5\)

\(\Rightarrow B\)

Filed Under: Critical Path Analysis (Y12) Tagged With: Band 4, smc-6916-55-Float Times