A project has 10 activities, labelled \(A\) to \(J\). The table below shows the immediate predecessor(s) for each activity. Each activity has a duration of at least one day.
\begin{array}{|c|c|}
\hline
\rule{0pt}{2.5ex}\textbf{Activity} & \textbf{Immediate}\\
&\textbf{predecessor(s)} \rule[-1ex]{0pt}{0pt}\\
\hline
\rule{0pt}{2.5ex}A \rule[-1ex]{0pt}{0pt}& - \\
\hline
\rule{0pt}{2.5ex}B \rule[-1ex]{0pt}{0pt}& - \\
\hline
\rule{0pt}{2.5ex}C \rule[-1ex]{0pt}{0pt}& A \\
\hline
\rule{0pt}{2.5ex}D \rule[-1ex]{0pt}{0pt}& B \\
\hline
\rule{0pt}{2.5ex}E \rule[-1ex]{0pt}{0pt}& B \\
\hline
\rule{0pt}{2.5ex}F \rule[-1ex]{0pt}{0pt}& D \\
\hline
\rule{0pt}{2.5ex}G \rule[-1ex]{0pt}{0pt}& D, E \\
\hline
\rule{0pt}{2.5ex}H \rule[-1ex]{0pt}{0pt}& C, F \\
\hline
\rule{0pt}{2.5ex}I \rule[-1ex]{0pt}{0pt}& E \\
\hline
\rule{0pt}{2.5ex}J \rule[-1ex]{0pt}{0pt}& G,H \\
\hline
\end{array}
Which one of the following statements about this project is not true?
- The earliest starting time of activity \(H\) could be two days.
- In the network for this project, there would be a dummy activity from the end of activity \(D\) to the start of activity \(G\).
- One of the paths through the network of this project is \(B D G J\).
- The latest starting time of activity \(E\) could be three days.
- The network for this project would require two dummy activities.
















