A project has 15 activities,
The directed network that represents this project is shown below.
The activities are not labelled.
The activity table that could represent this project is
Aussie Maths & Science Teachers: Save your time with SmarterEd
The Sunny Coast cricket clubroom is undergoing a major works project.
This project involves nine activities:
The table below shows the earliest start time (EST) and duration, in months, for each activity.
The immediate predecessor(s) is also shown.
The duration for activity
The information in the table above can be used to complete a directed network.
This network will require a dummy activity.
--- 0 WORK AREA LINES (style=lined) ---
--- 5 WORK AREA LINES (style=blank) ---
--- 2 WORK AREA LINES (style=lined) ---
--- 4 WORK AREA LINES (style=lined) ---
What is the minimum time, in months, that the project can be completed in? (1 mark)
--- 3 WORK AREA LINES (style=lined) ---
A project involves nine activities,
The immediate predecessor(s) of each activity is shown in the table below.
Activity | Immediate predecessor(s) |
|
A directed network for this project will require a dummy activity.
The dummy activity will be drawn from the end of
Andy, Brian and Caleb must complete three activities in total (K, L and M)
The table shows the person selected to complete each activity, the time it will take to complete the activity in minutes and the immediate predecessor for each activity.
All three activities must be completed in a total of 40 minutes.
The instant that Andy starts his activity, Caleb gets a telephone call.
The maximum time, in minutes, that Caleb can speak on the telephone before he must start his allocated activity is
A. 5
B. 13
C. 18
D. 24
E. 34
The five musicians are to record an album. This will involve nine activities.
The activities and their immediate predecessors are shown in the following table.
The duration of each activity is not yet known.
--- 0 WORK AREA LINES (style=lined) ---
There is only one critical path for this project.
--- 5 WORK AREA LINES (style=lined) ---
The following table gives the earliest start times (EST) and latest start times (LST) for three of the activities only. All times are in hours.
--- 2 WORK AREA LINES (style=lined) ---
The minimum time required for this project to be completed is 19 hours.
--- 2 WORK AREA LINES (style=lined) ---
The duration of activity
--- 3 WORK AREA LINES (style=lined) ---
A project will be undertaken in the wildlife park. This project involves the 13 activities shown in the table below. The duration, in hours, and predecessor(s) of each activity are also included in the table.
Activity
--- 0 WORK AREA LINES (style=lined) ---
--- 1 WORK AREA LINES (style=lined) ---
--- 1 WORK AREA LINES (style=lined) ---
--- 5 WORK AREA LINES (style=lined) ---
Explain the circumstances under which this statement will be true for this project. (1 mark)
--- 2 WORK AREA LINES (style=lined) ---
What will be the minimum completion time for the project? (1 mark)
--- 3 WORK AREA LINES (style=lined) ---
In the final challenge, each of four teams has to complete a construction project that involves activities
Table 1 shows the earliest start time (EST), latest start time (LST) and duration, in minutes, for each activity.
The immediate predecessor is also shown. The earliest start time for activity
--- 1 WORK AREA LINES (style=lined) ---
--- 2 WORK AREA LINES (style=lined) ---
--- 1 WORK AREA LINES (style=lined) ---
--- 2 WORK AREA LINES (style=lined) ---
--- 3 WORK AREA LINES (style=lined) ---
--- 1 WORK AREA LINES (style=lined) ---
a.
b. | ||
c.
d. | ||
e.
f.
A section of the Farnham showgrounds has flooded due to a broken water pipe. The public will be stopped from entering the flooded area until repairs are made and the area has been cleaned up.
The table below shows the nine activities that need to be completed in order to repair the water pipe. Also shown are some of the durations, Earliest Start Times (EST) and the immediate predecessors for the activities.
--- 2 WORK AREA LINES (style=lined) ---
--- 1 WORK AREA LINES (style=lined) ---
--- 1 WORK AREA LINES (style=lined) ---
It is more complicated to replace the broken water pipe (Activity
--- 2 WORK AREA LINES (style=lined) ---
Turning on the water to the showgrounds (Activity
--- 2 WORK AREA LINES (style=lined) ---
a. | ||
b.
c.
d.
e.