An upgrade to the supermarket requires the completion of 11 activities, \(A\) to \(K\). The directed network below shows these activities and their completion time, in weeks. The minimum completion time for the project is 29 weeks. --- 1 WORK AREA LINES (style=lined) --- --- 1 WORK AREA LINES (style=lined) --- Use the following information to answer parts c-e. A change is made to the order of activities. The table below shows the activities and their new latest starting times in weeks. \begin{array}{|c|c|} A dummy activity is now required in the network. --- 1 WORK AREA LINES (style=lined) ---
--- 1 WORK AREA LINES (style=lined) --- --- 1 WORK AREA LINES (style=lined) ---
\hline
\textbf{Activity} & \textbf{Latest Starting}\\
&\textbf{time} \text{(weeks)}\\
\hline A & 0 \\
\hline B & 2 \\
\hline C & 10 \\
\hline D & 9 \\
\hline E & 13 \\
\hline F & 14 \\
\hline G & 18 \\
\hline H & 17 \\
\hline I & 19 \\
\hline J & 25 \\
\hline K & 22 \\
\hline
\end{array}
NETWORKS, FUR2 2018 VCAA 3
At the Zenith Post Office all computer systems are to be upgraded.
This project involves 10 activities, `A` to `J`.
The directed network below shows these activities and their completion times, in hours.
- Determine the earliest starting time, in hours, for activity `I`. (1 mark)
--- 2 WORK AREA LINES (style=lined) ---
- The minimum completion time for the project is 15 hours.
Write down the critical path. (1 mark)
--- 1 WORK AREA LINES (style=lined) ---
- Two of the activities have a float time of two hours.
Write down these two activities. (1 mark)
--- 3 WORK AREA LINES (style=lined) ---
- For the next upgrade, the same project will be repeated but one extra activity will be added.
This activity has a duration of one hour, an earliest starting time of five hours and a latest starting time of 12 hours.Complete the following sentence by filling in the boxes provided. (1 mark)
--- 3 WORK AREA LINES (style=lined) ---
The extra activity could be represented on the network above by a directed edge from the
| end of activity |
|
to the start of activity |
|
NETWORKS, FUR2 2016 VCAA 3
A new skateboard park is to be built in Beachton.
This project involves 13 activities, `A` to `M`.
The directed network below shows these activities and their completion times in days.
- Determine the earliest start time for activity `M`. (1 mark)
--- 2 WORK AREA LINES (style=lined) ---
- The minimum completion time for the skateboard park is 15 days.
Write down the critical path for this project. (1 mark)
--- 1 WORK AREA LINES (style=lined) ---
- Which activity has a float time of two days? (1 mark)
--- 1 WORK AREA LINES (style=lined) ---
- The completion times for activities `E, F, G, I` and `J` can each be reduced by one day.
The cost of reducing the completion time by one day for these activities is shown in the table below.
What is the minimum cost to complete the project in the shortest time possible? (1 mark)
--- 2 WORK AREA LINES (style=lined) ---
- The original skateboard park project from part (a), before the reduction of time in any activity, will be repeated at another town named Campville, but with the addition of one extra activity.
The new activity, `N`, will take six days to complete and has a float time of one day.
Activity `N` will finish at the same time as the project.
i. Add activity `N` to the network below. (1 mark)
--- 0 WORK AREA LINES (style=lined) ---

ii. What is the latest start time for activity `N`? (1 mark)--- 3 WORK AREA LINES (style=lined) ---
NETWORKS, FUR2 2009 VCAA 4
A walkway is to be built across the lake.
Eleven activities must be completed for this building project.
The directed network below shows the activities and their completion times in weeks.
- What is the earliest start time for activity `E`? (1 mark)
--- 1 WORK AREA LINES (style=lined) ---
- Write down the critical path for this project. (1 mark)
--- 1 WORK AREA LINES (style=lined) ---
- The project supervisor correctly writes down the float time for each activity that can be delayed and makes a list of these times.
Determine the longest float time, in weeks, on the supervisor’s list. (1 mark)
--- 1 WORK AREA LINES (style=lined) ---
A twelfth activity, `L`, with duration three weeks, is to be added without altering the critical path.
Activity `L` has an earliest start time of four weeks and a latest start time of five weeks.
- Draw in activity `L` on the network diagram above. (1 mark)
--- 0 WORK AREA LINES (style=lined) ---
- Activity `L` starts, but then takes four weeks longer than originally planned.
Determine the total overall time, in weeks, for the completion of this building project. (1 mark)
--- 4 WORK AREA LINES (style=lined) ---




