The precedence table below shows the 12 activities required to complete a project. The duration in days and immediate predecessors are shown.
\begin{array}{|c|c|c|}
\hline \rule{0pt}{2.5ex}\ \ \textbf{Activity} \ \ & \ \ \textbf{Duration} \ \ & \textbf{Immediate predecessors} \\
\hline \rule{0pt}{2.5ex}A \rule[-1ex]{0pt}{0pt}& 4 & - \\
\hline \rule{0pt}{2.5ex}B \rule[-1ex]{0pt}{0pt}& 6 & A \\
\hline \rule{0pt}{2.5ex}C \rule[-1ex]{0pt}{0pt}& 8 & A \\
\hline \rule{0pt}{2.5ex}D \rule[-1ex]{0pt}{0pt}& 3 & A \\
\hline \rule{0pt}{2.5ex}E \rule[-1ex]{0pt}{0pt}& 9 & B\\
\hline \rule{0pt}{2.5ex}F \rule[-1ex]{0pt}{0pt}& 6 & C \\
\hline \rule{0pt}{2.5ex}G \rule[-1ex]{0pt}{0pt}& 7 & B, D, F \\
\hline \rule{0pt}{2.5ex}H \rule[-1ex]{0pt}{0pt}& 12 & C \\
\hline \rule{0pt}{2.5ex}I \rule[-1ex]{0pt}{0pt}& 6 & G, H \\
\hline \rule{0pt}{2.5ex}J \rule[-1ex]{0pt}{0pt}& 4 & E, I \\
\hline \rule{0pt}{2.5ex}K \rule[-1ex]{0pt}{0pt}& 3 & G, H \\
\hline \rule{0pt}{2.5ex}L \rule[-1ex]{0pt}{0pt}& 9 & J \\
\hline
\end{array}
The project is to be completed in minimum time.
- Sketch the network, identifying each activity and its duration, including any dummy activities. (3 marks)
--- 12 WORK AREA LINES (style=lined) ---
- Determine the critical path of the network. (1 mark)
--- 2 WORK AREA LINES (style=lined) ---



