A project involving nine activities is shown in the network diagram.
The duration of each activity is not yet known.
The following table gives the earliest start time (EST) and latest start time (LST) for three of the activities. All times are in hours.
\begin{array} {|c|c|c|}
\hline
\rule{0pt}{2.5ex} \textit{Activity} \rule[-1ex]{0pt}{0pt} & EST & LST \\
\hline
\rule{0pt}{2.5ex} A \rule[-1ex]{0pt}{0pt} & \ \ \ \ \ \ 0\ \ \ \ \ \ & \ \ \ \ \ \ 2\ \ \ \ \ \ \\
\hline
\rule{0pt}{2.5ex} C \rule[-1ex]{0pt}{0pt} & 0 & 1 \\
\hline
\rule{0pt}{2.5ex} I \rule[-1ex]{0pt}{0pt} & 12 & 12 \\
\hline
\end{array}
- What is the critical path? (1 mark)
--- 2 WORK AREA LINES (style=lined) ---
- The minimum time required for this project to be completed is 19 hours.
- What is the duration of activity \(I\)? (1 mark)
--- 2 WORK AREA LINES (style=lined) ---
- The duration of activity \(C\) is 3 hours.
- What is the maximum amount of time that could occur between the start of activity \(F\) and the end of activity \(H\)? (1 mark)
--- 2 WORK AREA LINES (style=lined) ---