MATRICES*, FUR1 2007 VCAA 8 MC
There are five teams,
The results are summarised in the directed graph below. An arrow from
In 2007, the team that had the highest number of two-step dominances was
A. team
B. team
C. team
D. team
E. team
NETWORKS, FUR1 2007 VCAA 7 MC
NETWORKS, FUR1 2007 VCAA 4 MC
NETWORKS, FUR1 2007 VCAA 1 MC
NETWORKS, FUR1 2009 VCAA 7 MC
Four workers, Anna, Bill, Caitlin and David, are each to be assigned a different task.
The table below gives the time, in minutes, that each worker takes to complete each of the four tasks.
The tasks are allocated so as to minimise the total time taken to complete the four tasks.
This total time, in minutes, is
A.
B.
C.
D.
E.
NETWORKS, FUR1 2009 VCAA 5-6 MC
The network shows the activities that are needed to complete a particular project.
Part 1
The total number of activities that need to be completed before activity
A.
B.
C.
D.
E.
Part 2
The duration of every activity is initially 5 hours. For an extra cost, the completion times of both activity
If this is done, the completion time for the project will be
A. decreased by 2 hours.
B. decreased by 3 hours.
C. decreased by 4 hours.
D. decreased by 6 hours.
E. unchanged.
NETWORKS, FUR1 2009 VCAA 4 MC
A connected planar graph has 10 edges and 10 faces.
The number of vertices for this graph is
NETWORKS, FUR1 2009 VCAA 1 MC
NETWORKS, FUR1 2011 VCAA 8 MC
NETWORKS, FUR1 2011 VCAA 3-4 MC
The map of Australia shows the six states, the Northern Territory and the Australian Capital Territory (ACT).
In the network diagram below, each of the vertices
Part 1
In the network diagram, the order of the vertex that represents the Australian Capital Territory (ACT) is
A.
B.
C.
D.
E.
Part 2
In the network diagram, Queensland is represented by
A. vertex A.
B. vertex B.
C. vertex C.
D. vertex D.
E. vertex E.
MATRICES*, FUR1 2011 VCAA 2 MC
The graph below shows the one-step dominances between four farm dogs, Kip, Lab, Max, and Nim.
In this graph, an arrow from Lab to Kip indicates that Lab has a one-step dominance over Kip.
From this graph, it can be concluded that Kip has a two-step dominance over
A. Max only.
B. Nim only.
C. Lab and Nim only.
D. all of the other three dogs.
E. none of the other three dogs.
NETWORKS, FUR1 2011 VCAA 1 MC
NETWORKS, FUR1 2012 VCAA 6 MC
NETWORKS, FUR1 2012 VCAA 5 MC
NETWORKS, FUR1 2012 VCAA 4 MC
The adjacency matrix above represents a planar graph with four vertices.
The number of faces (regions) on the planar graph is
A.
B.
C.
D.
E.
NETWORKS, FUR1 2012 VCAA 2 MC
MATRICES*, FUR1 2013 VCAA 5 MC
Four people, Ash (A), Binh (B), Con (C) and Dan (D), competed in a table tennis tournament.
In this tournament, each competitor played each of the other competitors once.
The results of the tournament are summarised in the directed graph below.
Each arrow shows the winner of a game played in the tournament. For example, the arrow from
In the tournament, each competitor was given a ranking that was determined by calculating the sum of their one-step and two-step dominances. The competitor with the highest sum is ranked number one (1). The competitor with the second-highest sum was ranked number two (2), and so on.
Using this method, the rankings of the competitors in this tournament were
A. Dan (1), Ash (2), Con (3), Binh (4)
B. Dan (1), Ash (2), Binh (3), Con (4)
C. Con (1), Dan (2), Ash (3), Binh (4)
D. Ash (1), Dan (2), Binh (3), Con (4)
E. Ash (1), Dan (2), Con (3), Binh (4)
NETWORKS, FUR1 2013 VCAA 2 MC
The number of edges needed to make a complete graph with four vertices is
A.
B.
C.
D.
E.
NETWORKS, FUR2 2006 VCAA 3
The five musicians are to record an album. This will involve nine activities.
The activities and their immediate predecessors are shown in the following table.
The duration of each activity is not yet known.
- Use the information in the table above to complete the network below by including activities
, and . (2 marks)
--- 0 WORK AREA LINES (style=lined) ---
There is only one critical path for this project.
- How many non-critical activities are there? (1 mark)
--- 5 WORK AREA LINES (style=lined) ---
The following table gives the earliest start times (EST) and latest start times (LST) for three of the activities only. All times are in hours.
- Write down the critical path for this project. (1 mark)
--- 2 WORK AREA LINES (style=lined) ---
The minimum time required for this project to be completed is 19 hours.
- What is the duration of activity
? (1 mark)
--- 2 WORK AREA LINES (style=lined) ---
The duration of activity
- Determine the maximum combined duration of activities
and . (1 mark)--- 3 WORK AREA LINES (style=lined) ---
MATRICES*, FUR2 2006 VCAA 2
The five musicians, George, Harriet, Ian, Josie and Keith, compete in a music trivia game.
Each musician competes once against every other musician.
In each game there is a winner and a loser.
The results are represented in the dominance matrix, Matrix 1, and also in the incomplete directed graph below.
On the directed graph an arrow from Harriet to George shows that Harriet won against George.
- Explain why the figures in bold in Matrix 1 are all zero. (1 mark)
--- 2 WORK AREA LINES (style=lined) ---
One of the edges on the directed graph is missing.
- Using the information in Matrix 1, draw in the missing edge on the directed graph above and clearly show its direction. (1 mark)
--- 0 WORK AREA LINES (style=lined) ---
The results of each trivia contest (one-step dominances) are summarised as follows.
In order to rank the musicians from first to last in the trivia contest, two-step (two-edge) dominances will be considered.
The following incomplete matrix, Matrix 2, shows two-step dominances.
- Explain the two-step dominance that George has over Ian. (1 mark)
--- 2 WORK AREA LINES (style=lined) ---
- Determine the value of the entry
in Matrix 2. (1 mark)
--- 2 WORK AREA LINES (style=lined) ---
- Taking into consideration both the one-step and two-step dominances, determine which musician was ranked first and which was ranked last in the trivia contest. (2 marks)
--- 5 WORK AREA LINES (style=lined) ---
NETWORKS, FUR2 2007 VCAA 4
A community centre is to be built on the new housing estate.
Nine activities have been identified for this building project.
The directed network below shows the activities and their completion times in weeks.
- Determine the minimum time, in weeks, to complete this project. (1 mark)
--- 2 WORK AREA LINES (style=lined) ---
- Determine the slack time, in weeks, for activity
. (2 marks)
--- 3 WORK AREA LINES (style=lined) ---
The builders of the community centre are able to speed up the project.
Some of the activities can be reduced in time at an additional cost.
The activities that can be reduced in time are
- Which of these activities, if reduced in time individually, would not result in an earlier completion of the project? (1 mark)
--- 2 WORK AREA LINES (style=lined) ---
The owner of the estate is prepared to pay the additional cost to achieve early completion.
The cost of reducing the time of each activity is $5000 per week.
The maximum reduction in time for each one of the five activities,
- Determine the minimum time, in weeks, for the project to be completed now that certain activities can be reduced in time. (1 mark)
--- 3 WORK AREA LINES (style=lined) ---
- Determine the minimum additional cost of completing the project in this reduced time. (1 mark)
--- 2 WORK AREA LINES (style=lined) ---
NETWORKS, FUR2 2007 VCAA 2
The estate has large open parklands that contain seven large trees.
The trees are denoted as vertices
Walking paths link the trees as shown.
The numbers on the edges represent the lengths of the paths in metres.
- Determine the sum of the degrees of the vertices of this network. (1 mark)
--- 2 WORK AREA LINES (style=lined) ---
-
One day Jamie decides to go for a walk that will take him along each of the paths between the trees.
He wishes to walk the minimum possible distance.
i. State a vertex at which Jamie could begin his walk? (1 mark)
--- 1 WORK AREA LINES (style=lined) ---
- ii. Determine the total distance, in metres, that Jamie will walk. (1 mark)
--- 2 WORK AREA LINES (style=lined) ---
Michelle is currently at
She wishes to follow a route that can be described as the shortest Hamiltonian circuit.
- Write down a route that Michelle can take. (1 mark)
--- 1 WORK AREA LINES (style=lined) ---
NETWORKS, FUR2 2007 VCAA 1
A new housing estate is being developed.
There are five houses under construction in one location.
These houses are numbered as points 1 to 5 below.
The builders require the five houses to be connected by electrical cables to enable the workers to have a supply of power on each site.
- What is the minimum number of edges needed to connect the five houses? (1 mark)
--- 1 WORK AREA LINES (style=lined) ---
- On the diagram above, draw a connected graph with this number of edges. (1 mark)
--- 0 WORK AREA LINES (style=lined) ---
NETWORKS, FUR1 2014 VCAA 6-7 MC
MATRICES*, FUR1 2014 VCAA 4 MC
The directed graph below shows the results of a chess competition between five players: Alex, Ben, Cindi, Donna and Elise.
Each arrow indicates the winner of individual games. For example, the arrow from Alex to Donna indicates that Alex beat Donna in their game.
The sum of their one-step and two-step dominances is calculated to give each player a dominance score. The dominance scores are then used to rank the players.
The ranking of the players in this competition, from highest to lowest dominance score, is
A. Ben, Elise, Donna, Alex, Cindi
B. Ben, Elise, Cindi, Donna, Alex
C. Ben, Elise, Donna, Cindi, Alex
D. Elise, Ben, Donna, Alex, Cindi
E. Elise, Ben, Donna, Cindi, Alex
NETWORKS, FUR1 2014 VCAA 3 MC
The diagram below shows the network of roads that Stephanie can use to travel between home and school.
The numbers on the roads show the time, in minutes, that it takes her to ride a bicycle along each road.
Using this network of roads, the shortest time that it will take Stephanie to ride her bicycle from home to school is
A.
B.
C.
D.
E.
NETWORKS, FUR1 2015 VCAA 9 MC
NETWORKS, FUR1 2015 VCAA 6 MC
The map below shows all road connections between five towns,
A graph, shown below, was constructed to represent this map.
A mistake has been made in constructing this graph.
This mistake can be corrected by
A. drawing another edge between
B. drawing a loop at
C. removing the loop at
D. removing one edge between
E. removing one edge between
NETWORKS, FUR2 2013 VCAA 3
The rangers at the wildlife park restrict access to the walking tracks through areas where the animals breed.
The edges on the directed network diagram below represent one-way tracks through the breeding areas. The direction of travel on each track is shown by an arrow. The numbers on the edges indicate the maximum number of people who are permitted to walk along each track each day.
- Starting at
, how many people, in total, are permitted to walk to each day? (1 mark)
--- 2 WORK AREA LINES (style=lined) ---
One day, all the available walking tracks will be used by students on a school excursion.
The students will start at
Students must remain in the same groups throughout the walk.
- i. Group 1 will have 17 students. This is the maximum group size that can walk together from
to .
Write down the path that group 1 will take. (1 mark)
--- 1 WORK AREA LINES (style=lined) ---
- ii. Groups 2, 3 and 4 will each take different paths from
to .
Complete the six missing entries shaded in the table below. (2 marks)
--- 4 WORK AREA LINES (style=lined) ---
NETWORKS, FUR2 2013 VCAA 2
A project will be undertaken in the wildlife park. This project involves the 13 activities shown in the table below. The duration, in hours, and predecessor(s) of each activity are also included in the table.
Activity
- Complete the network diagram above by inserting activity
. (1 mark)
--- 0 WORK AREA LINES (style=lined) ---
- Determine the earliest starting time of activity
. (1 mark)
--- 1 WORK AREA LINES (style=lined) ---
- Given that activity
is not on the critical path:
i. Write down the activities that are on the critical path in the order that they are completed. (1 mark)
--- 1 WORK AREA LINES (style=lined) ---
- ii. Find the latest starting time for activity
. (1 mark)
--- 5 WORK AREA LINES (style=lined) ---
- Consider the following statement.
‘If just one of the activities in this project is crashed by one hour, then the minimum time to complete the entire project will be reduced by one hour.’Explain the circumstances under which this statement will be true for this project. (1 mark)
--- 2 WORK AREA LINES (style=lined) ---
- Assume activity
is crashed by two hours.What will be the minimum completion time for the project? (1 mark)
--- 3 WORK AREA LINES (style=lined) ---
MATRICES*, FUR2 2008 VCAA 4
The children are taken to the zoo where they observe the behaviour of five young male lion cubs. The lion cubs are named Arnold, Barnaby, Cedric, Darcy and Edgar. A dominance hierarchy has emerged within this group of lion cubs. In the directed graph below, the directions of the arrows show which lions are dominant over others.
- Name the two pairs of lion cubs who have equal totals of one-step dominances. (2 marks)
--- 2 WORK AREA LINES (style=lined) ---
- Over which lion does Cedric have both a one-step dominance and a two-step dominance? (1 mark)
--- 1 WORK AREA LINES (style=lined) ---
In determining the final order of dominance, the number of one-step dominances and two-step dominances are added together.
- Complete the table below for the final order of dominance. (1 mark)
--- 3 WORK AREA LINES (style=lined) ---
Over time, the pattern of dominance changes until each lion cub has a one-step dominance over two other lion cubs.
- Determine the total number of two-step dominances for this group of five lion cubs. (1 mark)
--- 3 WORK AREA LINES (style=lined) ---
NETWORKS, FUR2 2008 VCAA 3
Each of four children is to be driven by his or her parents to one of four different concerts. The following table shows the distance that each car would have to travel, in kilometres, to each of the four concerts.
The concerts will be allocated so as to minimise the total distance that must be travelled to take the children to the concerts. The hungarian algorithm is to be used to find this minimum value.
- Step 1 of the hungarian algorithm is to subtract the minimum entry in each row from each element in the row. Complete step 1 for Tahlia by writing the missing values in the table below. (1 mark)
--- 0 WORK AREA LINES (style=lined) ---
After further steps of the hungarian algorithm have been applied, the table is as follows.
It is now possible to allocate each child to a concert.
- Explain why this table shows that Tahlia should attend Concert 2. (1 mark)
--- 2 WORK AREA LINES (style=lined) ---
- Determine the concerts that could be attended by James, Dante and Chanel to minimise the total distance travelled. Write your answers in the table below. (1 mark)
--- 0 WORK AREA LINES (style=lined) ---
- Determine the minimum total distance, in kilometres, travelled by the four cars. (1 mark)
--- 3 WORK AREA LINES (style=lined) ---
NETWORKS, FUR2 2008 VCAA 2
Four children, James, Dante, Tahlia and Chanel each live in a different town.
The following is a map of the roads that link the four towns,
- How many different ways may a vehicle travel from town
to town without travelling along any road more than once? (1 mark)
--- 5 WORK AREA LINES (style=lined) ---
James’ father has begun to draw a network diagram that represents all the routes between the four towns on the map. This is shown below.
In this network, vertices represent towns and edges represent routes between tow
- i. One more edge needs to be added to complete this network. Draw in this edge clearly on the diagram above. (1 mark)
--- 0 WORK AREA LINES (style=lined) ---
- ii. With reference to the network diagram, explain why a motorist at
could not drive each of these routes once only and arrive back at . (1 mark)
--- 3 WORK AREA LINES (style=lined) ---
NETWORKS, FUR2 2008 VCAA 1
James, Dante, Tahlia and Chanel are four children playing a game.
In this children’s game, seven posts are placed in the ground.
The network below shows distances, in metres, between the seven posts.
The aim of the game is to connect the posts with ribbon using the shortest length of ribbon.
This will be a minimal spanning tree.
- Draw in a minimal spanning tree for this network on the diagram below. (1 mark)
--- 0 WORK AREA LINES (style=lined) ---
- Determine the length, in metres, of this minimal spanning tree. (1 mark)
--- 2 WORK AREA LINES (style=lined) ---
- How many different minimal spanning trees can be drawn for this network? (1 mark)
--- 1 WORK AREA LINES (style=lined) ---
NETWORKS, FUR2 2009 VCAA 4
A walkway is to be built across the lake.
Eleven activities must be completed for this building project.
The directed network below shows the activities and their completion times in weeks.
- What is the earliest start time for activity
? (1 mark)
--- 1 WORK AREA LINES (style=lined) ---
- Write down the critical path for this project. (1 mark)
--- 1 WORK AREA LINES (style=lined) ---
- The project supervisor correctly writes down the float time for each activity that can be delayed and makes a list of these times.
Determine the longest float time, in weeks, on the supervisor’s list. (1 mark)
--- 1 WORK AREA LINES (style=lined) ---
A twelfth activity,
Activity
- Draw in activity
on the network diagram above. (1 mark)
--- 0 WORK AREA LINES (style=lined) ---
- Activity
starts, but then takes four weeks longer than originally planned.
Determine the total overall time, in weeks, for the completion of this building project. (1 mark)
--- 4 WORK AREA LINES (style=lined) ---
NETWORKS, FUR2 2009 VCAA 3
The city of Robville contains eight landmarks denoted as vertices
- Write down the degree of vertex
. (1 mark)
--- 1 WORK AREA LINES (style=lined) ---
- Steven wants to visit each landmark, but drive along each road only once. He will begin his journey at landmark
.- Michael was the best player in 2014 and he considered purchasing cricket equipment that was valued at $750.
- At which landmark must he finish his journey? (1 mark)
--- 1 WORK AREA LINES (style=lined) ---
-
Regardless of which route Steven decides to take, how many of the landmarks (including those at the start and finish) will he see on exactly two occasions? (1 mark)
--- 1 WORK AREA LINES (style=lined) ---
- Cathy decides to visit each landmark only once.
- Suppose she starts at
, then visits and finishes at . - Write down the order Cathy will visit the landmarks. (1 mark)
--- 2 WORK AREA LINES (style=lined) ---
- Suppose Cathy starts at
, then visits but does not finish at . - List three different ways that she can visit the landmarks. (1 mark)
--- 2 WORK AREA LINES (style=lined) ---
- Suppose she starts at
NETWORKS, FUR2 2009 VCAA 1
The city of Robville is divided into five suburbs labelled as
A lake which is situated in the city is shaded on the map.
An adjacency matrix is constructed to represent the number of land borders between suburbs.
- Explain why all values in the final row and final column are zero. (1 mark)
--- 1 WORK AREA LINES (style=lined) ---
In the network diagram below, vertices represent suburbs and edges represent land borders between suburbs.
The diagram has been started but is not finished.
- The network diagram is missing one edge and one vertex.
On the diagram
- i. draw the missing edge. (1 mark)
--- 0 WORK AREA LINES (style=lined) ---
- ii. draw and label the missing vertex. (1 mark)
--- 0 WORK AREA LINES (style=lined) ---
NETWORKS, FUR2 2010 VCAA 4
In the final challenge, each of four teams has to complete a construction project that involves activities
Table 1 shows the earliest start time (EST), latest start time (LST) and duration, in minutes, for each activity.
The immediate predecessor is also shown. The earliest start time for activity
- What is the least number of activities that must be completed before activity
can commence? (1 mark)
--- 1 WORK AREA LINES (style=lined) ---
- What is the earliest start time for activity
? (1 mark)
--- 2 WORK AREA LINES (style=lined) ---
- Write down all the activities that must be completed before activity
can commence. (1 mark)
--- 1 WORK AREA LINES (style=lined) ---
- What is the float time, in minutes, for activity
? (1 mark)
--- 2 WORK AREA LINES (style=lined) ---
- What is the shortest time, in minutes, in which this construction project can be completed? (1 mark)
--- 3 WORK AREA LINES (style=lined) ---
- Write down the critical path for this network. (1 mark)
--- 1 WORK AREA LINES (style=lined) ---
NETWORKS, FUR2 2010 VCAA 3
The following network diagram shows the distances, in kilometres, along the roads that connect six intersections
- If a cyclist started at intersection
and cycled along every road in this network once only, at which intersection would she finish? (1 mark)
--- 1 WORK AREA LINES (style=lined) ---
- The next challenge involves cycling along every road in this network at least once.
Teams have to start and finish at intersection
.
The blue team does this and cycles the shortest possible total distance.
i. Apart from intersection
, through which intersections does the blue team pass more than once? (1 mark)
--- 2 WORK AREA LINES (style=lined) ---
- ii. How many kilometres does the blue team cycle? (1 mark)
--- 2 WORK AREA LINES (style=lined) ---
- The red team does not follow the rules and cycles along a bush path that connects two of the intersections.
This route allows the red team to ride along every road only once.
Which two intersections does the bush path connect? (1 mark)
--- 2 WORK AREA LINES (style=lined) ---
NETWORKS, FUR2 2011 VCAA 4
Stormwater enters a network of pipes at either Dunlop North (Source 1) or Dunlop South (Source 2) and flows into the ocean at either Outlet 1 or Outlet 2.
On the network diagram below, the pipes are represented by straight lines with arrows that indicate the direction of the flow of water. Water cannot flow through a pipe in the opposite direction.
The numbers next to the arrows represent the maximum rate, in kilolitres per minute, at which stormwater can flow through each pipe.
- Complete the following sentence for this network of pipes by writing either the number 1 or 2 in each box. (1 mark)
--- 0 WORK AREA LINES (style=lined) ---
- Determine the maximum rate, in kilolitres per minute, that water can flow from these pipes into the ocean at Outlet 1 and Outlet 2. (2 marks)
--- 5 WORK AREA LINES (style=lined) ---
A length of pipe, show in bold on the network diagram below, has been damaged and will be replaced with a larger pipe.
- The new pipe must enable the greatest possible rate of flow of stormwater into the ocean from Outlet 2.
- What minimum rate of flow through the pipe, in kilolitres per minute, will achieve this? (1 mark)
--- 3 WORK AREA LINES (style=lined) ---
NETWORKS, FUR2 2011 VCAA 3
A section of the Farnham showgrounds has flooded due to a broken water pipe. The public will be stopped from entering the flooded area until repairs are made and the area has been cleaned up.
The table below shows the nine activities that need to be completed in order to repair the water pipe. Also shown are some of the durations, Earliest Start Times (EST) and the immediate predecessors for the activities.
- What is the duration of activity
? (1 mark)
--- 2 WORK AREA LINES (style=lined) ---
- What is the Earliest Start Time (EST) for activity
? (1 mark)
--- 1 WORK AREA LINES (style=lined) ---
- Once the water has been turned off (Activity
), which of the activities to could be delayed without affecting the shortest time to complete all activities? (1 mark)
--- 1 WORK AREA LINES (style=lined) ---
It is more complicated to replace the broken water pipe (Activity
- Determine the shortest time in which activities
to can now be completed. (1 mark)
--- 2 WORK AREA LINES (style=lined) ---
Turning on the water to the showgrounds (Activity
- With the increased duration of Activity
and Activity , determine the shortest time in which activities to can be completed. (1 mark)
--- 2 WORK AREA LINES (style=lined) ---
NETWORKS, FUR2 2011 VCAA 2
At the Farnham showgrounds, eleven locations require access to water. These locations are represented by vertices on the network diagram shown below. The dashed lines on the network diagram represent possible water pipe connections between adjacent locations. The numbers on the dashed lines show the minimum length of pipe required to connect these locations in metres.
All locations are to be connected using the smallest total length of water pipe possible.
- On the diagram, show where these water pipes will be placed. (1 mark)
--- 0 WORK AREA LINES (style=lined) ---
- Calculate the total length, in metres, of water pipe that is required. ( 1 mark)
--- 3 WORK AREA LINES (style=lined) ---
NETWORKS, FUR2 2011 VCAA 1
Aden, Bredon, Carrie, Dunlop, Enwin and Farnham are six towns.
The network shows the road connections and distances between these towns in kilometres.
- In kilometres, what is the shortest distance between Farnham and Carrie? (1 mark)
--- 2 WORK AREA LINES (style=lined) ---
- How many different ways are there to travel from Farnham to Carrie without passing through any town more than once? (1 mark)
--- 4 WORK AREA LINES (style=lined) ---
An engineer plans to inspect all of the roads in this network.
He will start at Dunlop and inspect each road only once.
- At which town will the inspection finish? (1 mark)
--- 1 WORK AREA LINES (style=lined) ---
Another engineer decides to start and finish her road inspection at Dunlop.
If an assistant inspects two of the roads, this engineer can inspect the remaining six roads and visit each of the other five towns only once.
- How many kilometres of road will the assistant need to inspect? (1 mark)
--- 3 WORK AREA LINES (style=lined) ---
Calculus, MET1 2006 VCAA 11
NETWORKS, FUR2 2014 VCAA 4
To restore a vintage train, 13 activities need to be completed.
The network below shows these 13 activities and their completion times in hours.
- Determine the earliest starting time of activity
. (1 mark)
--- 1 WORK AREA LINES (style=lined) ---
The minimum time in which all 13 activities can be completed is 21 hours.
- What is the latest starting time of activity
? (1 mark)
--- 3 WORK AREA LINES (style=lined) ---
- What is the float time of activity
? (1 mark)
--- 4 WORK AREA LINES (style=lined) ---
Just before they started restoring the train, the members of the club needed to add another activity,
Activity
Activity
- What is the latest starting time of activity
if it is not to increase the minimum completion time of the project? (1 mark)
--- 6 WORK AREA LINES (style=lined) ---
Activity
This may reduce the minimum completion time for the project, including activity
- Determine the least cost of crashing activity
to give the greatest reduction in the minimum completion time of the project. (1 mark)
--- 8 WORK AREA LINES (style=lined) ---
NETWORKS, FUR2 2014 VCAA 3
The diagram below shows a network of train lines between five towns: Attard, Bower, Clement, Derrin and Eden.
The numbers indicate the distances, in kilometres, that are travelled by train between connected towns.
Charlie followed an Eulerian path through this network of train lines.
- i. Write down the names of the towns at the start and at the end of Charlie’s path. (1 mark)
--- 1 WORK AREA LINES (style=lined) ---
ii. What distance did he travel? (1 mark)
--- 2 WORK AREA LINES (style=lined) ---
Brianna will follow a Hamiltonian path from Bower to Attard.
- What is the shortest distance that she can travel? (1 mark)
--- 2 WORK AREA LINES (style=lined) ---
The train line between Derrin and Eden will be removed. If one other train line is removed from the network, Andrew would be able to follow an Eulerian circuit through the network of train lines.
NETWORKS, FUR2 2014 VCAA 2
Planning a train club open day involves four tasks.
Table 1 shows the number of hours that each club member would take to complete these tasks.
The Hungarian algorithm will be used to allocate the tasks to club members so that the total time taken to complete the tasks is minimised.
The first step of the Hungarian algorithm is to subtract the smallest element in each row of Table 1 from each of the elements in that row.
The result of this step is shown in Table 2 below.
- Complete Table 2 by filling in the missing numbers for Andrew. (1 mark)
--- 0 WORK AREA LINES (style=lined) ---
After completing Table 2, Andrew decided that an allocation of tasks to minimise the total time taken was not yet possible using the Hungarian algorithm.
- Explain why Andrew made this decision. (1 mark)
--- 2 WORK AREA LINES (style=lined) ---
Table 3 shows the final result of all steps of the Hungarian algorithm.
- i. Which task should be allocated to Andrew? (1 mark)
--- 1 WORK AREA LINES (style=lined) ---
- ii. How many hours in total are used to plan for the open day? (1 mark)
--- 2 WORK AREA LINES (style=lined) ---
NETWORKS, FUR2 2015 VCAA 3
Nine activities are needed to prepare a daily delivery of groceries from the factory to the towns.
The duration, in minutes, earliest starting time (EST) and immediate predecessors for these activities are shown in the table below.
The directed network that shows these activities is shown below.
All nine of these activities can be completed in a minimum time of 26 minutes.
- What is the EST of activity
? (1 mark)
--- 1 WORK AREA LINES (style=lined) ---
- What is the latest starting time (LST) of activity
? (1 mark)
--- 1 WORK AREA LINES (style=lined) ---
- Given that the EST of activity
is 22 minutes, what is the duration of activity ? (1 mark)
--- 1 WORK AREA LINES (style=lined) ---
- Write down, in order, the activities on the critical path. (1 mark)
--- 1 WORK AREA LINES (style=lined) ---
- Activities
and can only be completed by either Cassie or Donna.One Monday, Donna is sick and both activities
and must be completed by Cassie. Cassie must complete one of these activities before starting the other.What is the least effect of this on the usual minimum preparation time for the delivery of groceries from the factory to the five towns? (1 mark)
--- 1 WORK AREA LINES (style=lined) ---
- Every Friday, a special delivery to the five towns includes fresh seafood. This causes a slight change to activity
, which then cannot start until activity has been completed.
i. Michael was the best player in 2014 and he considered purchasing cricket equipment that was valued at $750.
On the directed graph below, show this change without duplicating any activity? (1 mark)
- ii. What effect does the inclusion of seafood on Fridays have on the usual minimum preparation time for deliveries from the factory to the five towns? (1 mark)
--- 1 WORK AREA LINES (style=lined) ---
NETWORKS, FUR2 2015 VCAA 2
The factory supplies groceries to stores in five towns,
The edges of the graph represent roads that connect the towns and the factory.
The numbers on the edges indicate the distance, in kilometres, along the roads.
Vehicles may only travel along the road between towns
Each day, a van must deliver groceries from the factory to the five towns.
The first delivery must be to town
- i. The shortest possible circuit from the factory for this delivery run, starting from town
, is not Hamiltonian.
Complete the order in which these deliveries would follow this shortest possible circuit. (1 mark)
--- 0 WORK AREA LINES (style=lined) ---
factory –
– ___________________________ – factory - ii. With reference to the town names in your answer to part (a)(i), explain why this shortest circuit is not a Hamiltonian circuit. (1 mark)
--- 1 WORK AREA LINES (style=lined) ---
- Determine the length, in kilometres, of a delivery run that follows a Hamiltonian circuit from the factory to these stores if the first delivery is to town
. (1 mark)
--- 3 WORK AREA LINES (style=lined) ---
NETWORKS, FUR2 2015 VCAA 1
A factory requires seven computer servers to communicate with each other through a connected network of cables.
The servers,
The edges on the graph represent the cables that could connect adjacent computer servers.
The numbers on the edges show the cost, in dollars, of installing each cable.
- What is the cost, in dollars, of installing the cable between server
and server ? (1 mark)
--- 1 WORK AREA LINES (style=lined) ---
- What is the cheapest cost, in dollars, of installing cables between server
and server ? (1 mark)
--- 3 WORK AREA LINES (style=lined) ---
- An inspector checks the cables by walking along the length of each cable in one continuous path.
To avoid walking along any of the cables more than once, at which vertex should the inspector start and where would the inspector finish? (1 mark)--- 1 WORK AREA LINES (style=lined) ---
- The computer servers will be able to communicate with all the other servers as long as each server is connected by cable to at least one other server.
i. The cheapest installation that will join the seven computer servers by cable in a connected network follows a minimum spanning tree.Draw the minimum spanning tree on the plan below? (1 mark)
- ii. The factory’s manager has decided that only six connected computer servers will be needed, rather than seven.
How much would be saved in installation costs if the factory removed computer server from its minimum spanning tree network?
A copy of the graph above is provided below to assist with your working. (1 mark)
--- 5 WORK AREA LINES (style=lined) ---
MATRICES, FUR2 2006 VCAA 3
Market researchers claim that the ideal number of bookshops (
- Write the equations in matrix form using the following template. (1 mark)
- Do the equations have a unique solution? Provide an explanation to justify your response. (1 mark)
--- 3 WORK AREA LINES (style=lined) ---
- Write down an inverse matrix that can be used to solve these equations. (1 mark)
--- 3 WORK AREA LINES (style=lined) ---
- Solve the equations and hence write down the estimated ideal number of bookshops, sports shoe shops and music stores for a shopping centre. (1 mark)
--- 4 WORK AREA LINES (style=lined) ---
MATRICES, FUR2 2006 VCAA 2
A new shopping centre called Shopper Heaven (
Market research suggests that each shopping centre will have a regular customer base but attract and lose customers on a weekly basis as follows.
80% of Shopper Heaven customers will return to Shopper Heaven next week
12% of Shopper Heaven customers will shop at Eastown next week
8% of Shopper Heaven customers will shop at Noxland next week
76% of Eastown customers will return to Eastown next week
9% of Eastown customers will shop at Shopper Heaven next week
15% of Eastown customers will shop at Noxland next week
85% of Noxland customers will return to Noxland next week
10% of Noxland customers will shop at Shopper Heaven next week
5% of Noxland customers will shop at Eastown next week
- Enter this information into transition matrix
as indicated below (express percentages as proportions, for example write 76% as 0.76). (2 marks)
--- 0 WORK AREA LINES (style=lined) ---
During the week that Shopper Heaven opened, it had 300 000 customers.
In the same week, Eastown had 120 000 customers and Noxland had 180 000 customers.
- Write this information in the form of a column matrix,
, as indicated below. (1 mark)
--- 0 WORK AREA LINES (style=lined) ---
- Use
and to write and evaluate a matrix product that determines the number of customers expected at each of the shopping centres during the following week. (2 marks)
--- 4 WORK AREA LINES (style=lined) ---
- Show by calculating at least two appropriate state matrices that, in the long term, the number of customers expected at each centre each week is given by the matrix (2 marks)
--- 5 WORK AREA LINES (style=lined) ---
MATRICES, FUR2 2006 VCAA 1
A manufacturer sells three products,
The number of units of each product sold per month through each shop is given by the matrix
- Write down the order of matrix
. (1 mark)
--- 1 WORK AREA LINES (style=lined) ---
The matrix
- i. Evaluate the matrix
, where . (1 mark)
--- 3 WORK AREA LINES (style=lined) ---
- ii. What information does the elements of matrix
provide? (1 mark)
--- 2 WORK AREA LINES (style=lined) ---
- Explain why the matrix
is not defined. (1 mark)
--- 2 WORK AREA LINES (style=lined) ---
MATRICES, FUR2 2007 VCAA 2
To study the life-and-death cycle of an insect population, a number of insect eggs (
The initial state of this population can be described by the column matrix
A row has been included in the state matrix to allow for insects and eggs that die (
- What is the total number of insects in the population (including eggs) at the beginning of the study? (1 mark)
--- 1 WORK AREA LINES (style=lined) ---
In this population
-
- eggs may die, or they may live and grow into juveniles
- juveniles may die, or they may live and grow into adults
- adults will live a period of time but they will eventually die.
In this population, the adult insects have been sterilised so that no new eggs are produced. In these circumstances, the life-and-death cycle of the insects can be modelled by the transition matrix
- What proportion of eggs turn into juveniles each week? (1 mark)
--- 1 WORK AREA LINES (style=lined) ---
-
- Evaluate the matrix product
(1 mark)
--- 1 WORK AREA LINES (style=lined) ---
- Write down the number of live juveniles in the population after one week. (1 mark)
--- 3 WORK AREA LINES (style=lined) ---
- Determine the number of live juveniles in the population after four weeks. Write your answer correct to the nearest whole number. (1 mark)
--- 1 WORK AREA LINES (style=lined) ---
- After a number of weeks there will be no live eggs (less than one) left in the population.
- When does this first occur? (1 mark)
--- 4 WORK AREA LINES (style=lined) ---
- Write down the exact steady-state matrix for this population. (1 mark)
--- 3 WORK AREA LINES (style=lined) ---
- Evaluate the matrix product
- If the study is repeated with unsterilised adult insects, eggs will be laid and potentially grow into adults.
- Assuming 30% of adults lay eggs each week, the population matrix after one week,
, is now given by - where
and
- Determine
(1 mark)
--- 3 WORK AREA LINES (style=lined) ---
- This pattern continues. The population matrix after
weeks, , is given by - Determine the number of live eggs in this insect population after two weeks. (1 mark)
--- 3 WORK AREA LINES (style=lined) ---
- Determine
MATRICES, FUR2 2007 VCAA 1
The table below displays the energy content and amounts of fat, carbohydrate and protein contained in a serve of four foods: bread, margarine, peanut butter and honey.
- Write down a 2 x 3 matrix that displays the fat, carbohydrate and protein content (in columns) of bread and margarine. (1 mark)
--- 2 WORK AREA LINES (style=lined) ---
and are two matrices defined as follows.
- Evaluate the matrix product
. (1 mark)
--- 3 WORK AREA LINES (style=lined) ---
-
Determine the order of matrix product
. (1 mark)
--- 1 WORK AREA LINES (style=lined) ---
- Evaluate the matrix product
Matrix
Matrix
-
- Explain the information that the matrix product
provides. (1 mark)
--- 2 WORK AREA LINES (style=lined) ---
- Explain the information that the matrix product
- The number of serves of bread (
), margarine ( ), peanut butter ( ) and honey ( ) that contain, in total, 53 grams of fat, 101.5 grams of carbohydrate, 28.5 grams of protein and 3568 kilojoules of energy can be determined by solving the matrix equation
Solve the matrix equation to find the values , , and . (2 marks)
--- 4 WORK AREA LINES (style=lined) ---
MATRICES, FUR2 2009 VCAA 4
A series of extra rehearsals commenced in April. Each week participants could choose extra dancing rehearsals or extra singing rehearsals.
A matrix equation used to determine the number of students expected to attend these extra rehearsals is given by
where
The attendance matrix for the first week of extra rehearsals is given by
- Calculate the number of students who are expected to attend the extra singing rehearsals in week 3. (1 mark)
--- 3 WORK AREA LINES (style=lined) ---
- Of the students who attended extra rehearsals in week 3, how many are not expected to return for any extra rehearsals in week 4? (1 mark)
--- 3 WORK AREA LINES (style=lined) ---
MATRICES, FUR2 2009 VCAA 3
In 2009, the school entered a Rock Eisteddfod competition.
When rehearsals commenced in February, all students were asked whether they thought the school would make the state finals. The students’ responses, ‘yes’, ‘no’ or ‘undecided’ are shown in the initial state matrix
- How many students attend this school? (1 mark)
--- 2 WORK AREA LINES (style=lined) ---
Each week some students are expected to change their responses. The changes in their responses from one week to the next are modelled by the transition matrix
The following diagram can also be used to display the information represented in the transition matrix
-
- Complete the diagram above by writing the missing percentage in the shaded box. (1 mark)
--- 0 WORK AREA LINES (style=lined) ---
- Of the students who respond ‘yes’ one week, what percentage are expected to respond ‘undecided’ the next week when asked whether they think the school will make the state finals? (1 mark)
--- 1 WORK AREA LINES (style=lined) ---
- In total, how many students are not expected to have changed their response at the end of the first week? (2 marks)
--- 2 WORK AREA LINES (style=lined) ---
- Complete the diagram above by writing the missing percentage in the shaded box. (1 mark)
- Evaluate the product
, where is the state matrix at the end of the first week. (1 mark)
--- 3 WORK AREA LINES (style=lined) ---
- How many students are expected to respond ‘yes’ at the end of the third week when asked whether they think the school will make the state finals? (1 mark)
--- 3 WORK AREA LINES (style=lined) ---
MATRICES, FUR2 2009 VCAA 2
Tickets for the function are sold at the school office, the function hall and online.
Different prices are charged for students, teachers and parents.
Table 1 shows the number of tickets sold at each place and the total value of sales.
For this function
-
- student tickets cost
- teacher tickets cost
- parent tickets cost
.
- student tickets cost
- Use the information in Table 1 to complete the following matrix equation by inserting the missing values in the shaded boxes. (1 mark)
--- 0 WORK AREA LINES (style=lined) ---
- Use the matrix equation to find the cost of a teacher ticket to the school function. (2 marks)
--- 4 WORK AREA LINES (style=lined) ---
MATRICES, FUR2 2010 VCAA 4
The Dinosaurs (
The matrix
The number of people expected to attend the second game for each team can be determined using the matrix equation
where
-
- Determine
, the attendance matrix for the second game. (1 mark)
--- 2 WORK AREA LINES (style=lined) ---
- Every person who attends either the second Dinosaur game or the second Scorpion game will be given a free cap. How many caps, in total, are expected to be given away? (1 mark)
--- 2 WORK AREA LINES (style=lined) ---
- Determine
Assume that the attendance matrices for successive games can be determined as follows.
and so on such that
- Determine the attendance matrix (with the elements written correct to the nearest whole number) for game 10. (1 mark)
--- 3 WORK AREA LINES (style=lined) ---
- Describe the way in which the number of people attending the Dinosaurs’ games is expected to change over the next 80 or so games. (1 mark)
--- 3 WORK AREA LINES (style=lined) ---
The attendance at the first Dinosaur game was 2000 people and the attendance at the first Scorpion game was 1000 people.
Suppose, instead, that 2000 people attend the first Dinosaur game, and 1800 people attend the first Scorpion game.
- Describe the way in which the number of people attending the Dinosaurs’ games is expected to change over the next 80 or so games. (1 mark)
--- 3 WORK AREA LINES (style=lined) ---
- « Previous Page
- 1
- …
- 68
- 69
- 70
- 71
- 72
- …
- 90
- Next Page »