A project involves nine activities, `A` to `I`.
The immediate predecessor(s) of each activity is shown in the table below.
\begin{array} {|c|c|}
\hline \ \ \textbf{Activity}\ \ & \textbf{Immediate} \\ & \textbf{predecessor(s)} \\
\hline \rule{0pt}{2.5ex} A \rule[-1ex]{0pt}{0pt} & - \\
\hline \rule{0pt}{2.5ex} B \rule[-1ex]{0pt}{0pt} & A \\
\hline \rule{0pt}{2.5ex} C \rule[-1ex]{0pt}{0pt} & A \\
\hline \rule{0pt}{2.5ex} D \rule[-1ex]{0pt}{0pt} & B \\
\hline \rule{0pt}{2.5ex} E \rule[-1ex]{0pt}{0pt} & B, C \\
\hline \rule{0pt}{2.5ex} F \rule[-1ex]{0pt}{0pt} & D \\
\hline \rule{0pt}{2.5ex} G \rule[-1ex]{0pt}{0pt} & D \\
\hline \rule{0pt}{2.5ex} H \rule[-1ex]{0pt}{0pt} & E, F \\
\hline \rule{0pt}{2.5ex} I \rule[-1ex]{0pt}{0pt} & G, H \\
\hline \end{array}
A directed network for this project will require a dummy activity.
Sketch the network diagram, clearly identifying the dummy activity. (3 marks)